5726 1/2 S WILTON PL 90062
Certificate Information: 5726 1/2 S WILTON PL 90062
- Application / Permit
- 20014-10000-03388
- Plan Check / Job No.
- B20LA14294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH (N) ADDITION TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 11/4/2020
- Issuing Office
- Current Status
- Issued on 11/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | KEVIN MORALES |
| Corrections Issued | 9/9/2020 | KEVIN MORALES |
| Quality Review Completed | 9/16/2020 | EUGENE BARBEAU |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| Plan Check Approved | 10/30/2020 | KEVIN MORALES |
| Issued | 11/4/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/9/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/14/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 10/19/2020 | KURT CORRAL |
Contact Information
| Architect | Kazanjian,, Natalia Noyemi; Lic. No.: C34684 | 1204 DON JOSE DRIVE GLENDALE, CA 91207 |
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/3/2021 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/1/2021 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 7/1/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 7/6/2021 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/26/2021 | Approved | SABAS ALONSO |
| METHANE-Barrier | 8/26/2021 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 8/26/2021 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 4/28/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 4/27/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/18/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/18/2024 | Corrections Issued | JOSEPH MCGARRY |
| Pre-Inspection | 3/19/2024 | Corrections Issued | CRAIG DAVIS |