5726 1/2 S WILTON PL 90062

Certificate Information: 5726 1/2 S WILTON PL 90062

Application / Permit
20014-10000-03388
Plan Check / Job No.
B20LA14294
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH (N) ADDITION TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
Issued on 11/4/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 KEVIN MORALES
Corrections Issued 9/9/2020 KEVIN MORALES
Quality Review Completed 9/16/2020 EUGENE BARBEAU
Building Plans Picked Up 9/24/2020 APPLICANT
Plan Check Approved 10/30/2020 KEVIN MORALES
Issued 11/4/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/9/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 10/9/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/14/2020 JEANIE LAM
Sewer availability Cleared 10/14/2020 JEANIE LAM
Hydrant and Access approval Cleared 10/19/2020 KURT CORRAL

Contact Information

Architect Kazanjian,, Natalia Noyemi; Lic. No.: C34684 1204 DON JOSE DRIVE      GLENDALE, CA 91207
Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/3/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/1/2021 Corrections Issued FREDDIE RIVERA
Underground Mechanical 7/1/2021 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 7/6/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 7/6/2021 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 7/16/2021 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/26/2021 Approved SABAS ALONSO
METHANE-Barrier 8/26/2021 Approved SABAS ALONSO
METHANE-Subgrade 8/26/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 4/28/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 4/27/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 3/18/2024 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/18/2024 Corrections Issued JOSEPH MCGARRY
Pre-Inspection 3/19/2024 Corrections Issued CRAIG DAVIS