138 1/2 W 79TH ST 90003

Certificate Information: 138 1/2 W 79TH ST 90003

Application / Permit
20014-10000-03380
Plan Check / Job No.
B20LA14275
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO CONVERT STORAGE TO ADU
Permit Issued
Issued on 2/16/2021
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/19/2020 SAMUEL GONZALEZ
Corrections Issued 8/20/2020 SAMUEL GONZALEZ
Plan Check Approved 1/19/2021 DANIEL YIP
Issued 2/16/2021 APPLICANT
Building Plans Picked Up 12/16/2021 APPLICANT
CofO in Progress 4/26/2023 LILIANA PORTILLO
Permit Finaled 5/11/2023 DEROLD HAUFF
CofO Issued 5/11/2023 DEROLD HAUFF
Permit Finaled 5/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/9/2020 MATTHEW CRAIG
Address approval Cleared 10/20/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 10/20/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/2/2020 JEANIE LAM
Sewer availability Cleared 11/2/2020 JEANIE LAM
Construction near power lines Cleared 1/6/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/2/2021 No Access for Inspection JESUS PINEDA
Footing/Foundation/Slab 9/22/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 9/22/2021 Corrections Issued DAVID FEILER
Pre-Inspection 10/5/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/20/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 1/25/2022 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 1/25/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Approved LILIANA PORTILLO
Green Building Rough 2/3/2022 Not Ready for Inspection LILIANA PORTILLO
Pre-Inspection 3/23/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Rough 5/12/2022 Corrections Issued LILIANA PORTILLO
Gas Test 5/12/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 5/12/2022 Corrections Issued LILIANA PORTILLO
Sewer 5/12/2022 Approved LILIANA PORTILLO
Underground Mechanical 5/12/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 5/20/2022 Approved LILIANA PORTILLO
Gas Test 5/20/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 5/20/2022 Approved LILIANA PORTILLO
Underground Mechanical 5/20/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/26/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/6/2022 Approved LILIANA PORTILLO
Green Building Rough 6/6/2022 Approved LILIANA PORTILLO
HVAC-Rough 6/6/2022 Approved LILIANA PORTILLO
Drywall Nailing 7/6/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/6/2022 Approved LILIANA PORTILLO
Final 10/26/2022 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 10/26/2022 Approved LILIANA PORTILLO
Green Building Final 10/26/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 10/26/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 10/26/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/3/2022 Approved LILIANA PORTILLO
Final 11/3/2022 Conditional Approval LILIANA PORTILLO
HVAC-Final 11/3/2022 Approved LILIANA PORTILLO
PLUMBING-Final 11/3/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved LILIANA PORTILLO
Final 11/9/2022 Corrections Issued LILIANA PORTILLO
Final 3/10/2023 Conditional Approval LILIANA PORTILLO
Final 3/14/2023 Corrections Issued LILIANA PORTILLO
Final 4/26/2023 OK to Issue CofO LILIANA PORTILLO