14109 S AINSWORTH ST 90247

Certificate Information: 14109 S AINSWORTH ST 90247

Application / Permit
20014-10000-03348
Plan Check / Job No.
B20LA14170
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 1-STORY GARAGE TO 2-STORY ACCESSORY DWELLING UNIT WITH ADDITION TO GROUND FLOOR AND SECOND STORY.
Permit Issued
Issued on 6/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 CRYSTEL MAALOUF
Corrections Issued 9/16/2020 CRYSTEL MAALOUF
Quality Review Completed 10/14/2020 TU HUA
Applicant returned to address corrections 1/29/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 2/2/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 2/25/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 3/17/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 4/7/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 4/13/2022 CRYSTEL MAALOUF
Building Plans Picked Up 4/15/2022 APPLICANT
Plan Check Approved 5/5/2022 CRYSTEL MAALOUF
Issued 6/1/2022 APPLICANT
CofO in Progress 3/7/2023 JAMES CHAVEZ
No Progress 3/9/2023 ANSON MAGLASANG
CofO in Progress 5/25/2023 JAMES CHAVEZ
Permit Finaled 5/25/2023 ANSON MAGLASANG
CofO Issued 5/25/2023 ANSON MAGLASANG
Permit Finaled 5/25/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/2/2020 CHINH DINH
Roof/Waste drainage to street Cleared 10/2/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 12/15/2020 CHINH DINH
Sewer availability Cleared 12/15/2020 CHINH DINH
Low Impact Development Cleared 4/20/2022 MARCO SANCHEZ

Contact Information

Contractor Golden Construction Group Llc; Lic. No.: 1078364-B 16814 CITRONIA STREET      NORTHRIDGE, CA 91343
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/28/2022 Approved JOHN KLARIN
METHANE-Barrier 6/28/2022 Approved JOHN KLARIN
METHANE-Subgrade 6/28/2022 Approved JOHN KLARIN
Sewer 6/28/2022 Partial Approval JOHN KLARIN
PLUMBING-Rough 7/8/2022 Approved JOHN KLARIN
Wood Frame 7/8/2022 Approved JOHN KLARIN
Insulation 7/12/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 8/16/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/1/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 9/1/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 9/1/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 9/1/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 9/1/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 9/1/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/14/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 9/14/2022 Approved JOHN KLARIN
Green Building Rough 9/14/2022 Approved JOHN KLARIN
HVAC-Rough 9/14/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 9/14/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 9/14/2022 Approved JOHN KLARIN
Insulation 9/26/2022 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/26/2022 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 10/5/2022 Conditional Approval EUGENE CASSIDY
Drywall Nailing 10/7/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 10/7/2022 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Final 12/13/2022 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 12/13/2022 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 12/13/2022 Approved JAMES CHAVEZ
Green Building Final 12/15/2022 Corrections Issued JAMES CHAVEZ
Final 12/21/2022 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved JAMES CHAVEZ
Final 12/30/2022 OK to Issue CofO JAMES CHAVEZ
Green Building Final 12/30/2022 Approved JAMES CHAVEZ
Special/Order Compliance 3/10/2023 Corrections Issued JAMES CHAVEZ