10521 N MATHER AVE 91040
Certificate Information: 10521 N MATHER AVE 91040
- Application / Permit
- 20014-10000-03343
- Plan Check / Job No.
- B20LA14146
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION(5 ft x 9.83 ft, BED/BATH ROOM) AND ENCLOSE (E) PATIO (6FT X 14FT) WITH STAIRS TO EXISTING ONE STORY SINGLE FAMILY DEWLLING.
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 9/9/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 4/8/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 8/8/2021 | AUNG SOE |
| Plan Check Approved | 8/25/2021 | TSE MING HUANG |
| Building Plans Picked Up | 8/26/2021 | APPLICANT |
| Issued | 10/8/2021 | APPLICANT |
| CofO in Progress | 5/31/2022 | LEO MILBAUER |
| Permit Finaled | 12/29/2022 | DAVID JAMES |
| CofO Issued | 12/29/2022 | DAVID JAMES |
| Permit Finaled | 12/29/2022 | DAVID JAMES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 10/5/2020 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 10/16/2020 | CHRISTINE BUSTILLOS |
| Grading Pre-Inspection | Cleared | 8/8/2021 | SAMUEL GONZALEZ |
| Hold | Cleared | 10/18/2021 | JAZELLE A TRINIDAD |
Contact Information
| Contractor | South Pacific Development Construction Inc; Lic. No.: 1063751-B | 14926 TOUCHWOOD AVE BELLFLOWER, CA 90706 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/2/2021 | Corrections Issued | JASON BRANNON |
| Excavation/Setback/Form/Re-Bar | 11/30/2021 | Approved | EMIL ALEXANDRIAN |
| Footing/Foundation/Slab | 11/30/2021 | Approved | EMIL ALEXANDRIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Approved | EMIL ALEXANDRIAN |
| ELECTRICAL-Rough | 1/13/2022 | Approved | JASON BRANNON |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Approved | JASON BRANNON |
| PLUMBING-Rough | 1/13/2022 | Approved | JASON BRANNON |
| Shower Pan | 1/13/2022 | Approved | JASON BRANNON |
| Insulation | 1/18/2022 | No Access for Inspection | JASON BRANNON |
| Interior/Exterior Lathing | 1/18/2022 | Not Ready for Inspection | JASON BRANNON |
| Insulation | 1/19/2022 | Approved | JASON BRANNON |
| Interior/Exterior Lathing | 1/19/2022 | Approved | JASON BRANNON |
| Drywall Nailing | 1/21/2022 | Approved | EMIL ALEXANDRIAN |
| Interior/Exterior Lathing | 1/21/2022 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 4/14/2022 | Approved | JASON BRANNON |
| ELECTRICAL-Final | 4/14/2022 | Approved | JASON BRANNON |
| Final | 4/14/2022 | Conditional Approval | JASON BRANNON |
| PLUMBING-Final | 4/14/2022 | Approved | JASON BRANNON |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Approved | JASON BRANNON |
| Smoke Detectors | 4/14/2022 | Approved | JASON BRANNON |