1504 N AVENUE 50 90042

Certificate Information: 1504 N AVENUE 50 90042

Application / Permit
20014-10000-03331
Plan Check / Job No.
B20LA14101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLOOR ADDITION OF 45 SF AND 2ND STORY ADDITION OF 499 SF TO EXISTING 1-STORY SFD. INTERIOR REMODEL ON 1ST FLOOR WITH ADDING NEW COVERED PATIO 37 SF IN THE REAR OF BUILDING.
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 CHUNG-WEN CHUANG
Corrections Issued 9/21/2020 CHUNG-WEN CHUANG
Quality Review Completed 9/28/2020 KESETE HAREGOT
Building Plans Picked Up 9/28/2020 APPLICANT
Applicant returned to address corrections 12/28/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 8/17/2021 CHUNG-WEN CHUANG
Plan Check Approved 8/25/2021 CHUNG-WEN CHUANG
Issued 9/7/2021 APPLICANT
CofO in Progress 6/26/2024 ALIZAH MAYAGOITIA
Permit Finaled 6/27/2024 DEROLD HAUFF
CofO Issued 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2021 ELAINE LEI
Sewer availability Cleared 1/22/2021 ELAINE LEI
Low Impact Development Cleared 8/2/2021 SARAH YOUSSEF
Grading Pre-Inspection Cleared 8/18/2021 ROBERT HUGHES
Roof/Waste drainage to street Cleared 8/21/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/1/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Approval KATHRYN BUTTERWORTH
Special/Order Compliance 1/25/2022 No Violation (special insp) AMY COLIN
Special/Order Compliance 2/3/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 2/4/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 2/4/2022 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 2/4/2022 Corrections Issued CRAIG VAUGHAN
Underground Mechanical 2/4/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 2/4/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 2/11/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 2/11/2022 Approved CRAIG VAUGHAN
HVAC-Rough 2/11/2022 Approved CRAIG VAUGHAN
Insulation 2/17/2022 Approved CRAIG VAUGHAN
Drywall Nailing 2/25/2022 Approved KATHRYN BUTTERWORTH
Green Building Rough 2/25/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 2/25/2022 Partial Approval KATHRYN BUTTERWORTH
Interior/Exterior Lathing 3/17/2022 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 3/17/2022 Approved KATHRYN BUTTERWORTH
Sewer 5/17/2022 Approved SCOTT FINNILA
Service/Power Release 7/20/2022 Corrections Issued HAMIK HARTOUNIAN
Gas Test 8/11/2022 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/4/2024 Approved ALIZAH MAYAGOITIA
Final 3/4/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/4/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 3/4/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 3/4/2024 Approved ALIZAH MAYAGOITIA
Final 4/15/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 4/15/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Approved ALIZAH MAYAGOITIA
Final 6/24/2024 Conditional Approval ALIZAH MAYAGOITIA
Final 6/26/2024 OK to Issue CofO ALIZAH MAYAGOITIA