1504 N AVENUE 50 90042
Certificate Information: 1504 N AVENUE 50 90042
- Application / Permit
- 20014-10000-03331
- Plan Check / Job No.
- B20LA14101
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST FLOOR ADDITION OF 45 SF AND 2ND STORY ADDITION OF 499 SF TO EXISTING 1-STORY SFD. INTERIOR REMODEL ON 1ST FLOOR WITH ADDING NEW COVERED PATIO 37 SF IN THE REAR OF BUILDING.
- Permit Issued
- Issued on 9/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 9/21/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 9/28/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
| Applicant returned to address corrections | 12/28/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 8/17/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 8/25/2021 | CHUNG-WEN CHUANG |
| Issued | 9/7/2021 | APPLICANT |
| CofO in Progress | 6/26/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
| CofO Issued | 6/27/2024 | DEROLD HAUFF |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | ELAINE LEI |
| Sewer availability | Cleared | 1/22/2021 | ELAINE LEI |
| Low Impact Development | Cleared | 8/2/2021 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 8/18/2021 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 8/21/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 1/25/2022 | No Violation (special insp) | AMY COLIN |
| Special/Order Compliance | 2/3/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/4/2022 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 2/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 2/4/2022 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 2/4/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/11/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/11/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 2/11/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 2/17/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/25/2022 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/25/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 3/17/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 3/17/2022 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 5/17/2022 | Approved | SCOTT FINNILA |
| Service/Power Release | 7/20/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 8/11/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 3/4/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/15/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 4/15/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 6/24/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 6/26/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |