329-329 1/2 W 47TH ST 90037
Certificate Information: 329-329 1/2 W 47TH ST 90037
- Application / Permit
- 20014-10000-03327
- Plan Check / Job No.
- B20LA14089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADU addition to existing single family dwelling per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2020 | TSE MING HUANG |
| Plan Check Approved | 11/23/2020 | SHANGQIN XIE |
| Issued | 2/23/2021 | APPLICANT |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| CofO in Progress | 9/14/2021 | DAVID FEILER |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| CofO Issued | 9/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | THOMAS LANG |
| Permit | Cleared | 9/24/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | THOMAS LANG |
| Sewer availability | Cleared | 9/25/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2020 | THOMAS LANG |
| Tenant Habitability Plan | Cleared | 11/12/2020 | MICHAEL GREGERSON |
Contact Information
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/12/2021 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 4/12/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/6/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/6/2021 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 5/6/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/6/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 5/13/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 5/13/2021 | Approved | WILLIAM WREN |
| Pre-Inspection | 5/13/2021 | Partial Inspection | AMY COLIN |
| Drywall Nailing | 5/26/2021 | Approved | WILLIAM WREN |
| Gas Test | 6/9/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/9/2021 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 6/9/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/20/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 7/20/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 7/20/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 7/20/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 7/20/2021 | Approved | SCOTT FINNILA |
| Smoke Detectors | 7/20/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 7/28/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/28/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 7/28/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Final | 7/28/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 7/28/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/9/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Final | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Final | 8/13/2021 | Partial Inspection | JOAQUIN GREENOUGH |
| MERV13>=Final | 8/13/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Final | 8/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 9/14/2021 | OK to Issue CofO | DAVID FEILER |