6029 1/2 W ELEANOR AVE 90038
Certificate Information: 6029 1/2 W ELEANOR AVE 90038
- Application / Permit
- 20014-10000-03302
- Plan Check / Job No.
- B20LA13947
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION & ADDITIO OF DETACHED GARAGE INTO ADU PER LAMC 12.22A33 (c) & (d) Comply with Department Order effective date 03/11/2019.
- Permit Issued
- Issued on 10/19/2020
- Issuing Office
- Current Status
- CofO Issued on 1/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/2/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/10/2020 | JASON HEALEY |
| Building Plans Picked Up | 9/14/2020 | APPLICANT |
| Plan Check Approved | 10/19/2020 | MAHNAZ NOURHASHEMI |
| Issued | 10/19/2020 | APPLICANT |
| CofO in Progress | 1/26/2021 | JEFFREY CORPUZ |
| CofO Issued | 1/26/2021 | ARMOND GREGORYONA |
| Permit Finaled | 1/26/2021 | ARMOND GREGORYONA |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/25/2020 | MARTIN FRAGOSO |
| Address approval | Cleared | 9/29/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/29/2020 | CECILIO NAVARRO |
| ZI | Cleared | 9/30/2020 | HERMINIGILDO AGUSTIN |
| Hydrant and Access approval | Cleared | 10/7/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Perez,, Thomas E; Lic. No.: C67549 | 1521 FRANZEN AVE SANTA ANA, CA 92703 |
Inspector Information
| EDMUND LUM, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUCIANO GAUNA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAIME RIOS, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDEY CHAPARRO, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN BARNES, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| PATRICK LIEBREGT, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GLEN RAND, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAWN ESHBACH, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GABRIEL HERRERA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 11/2/2020 | Approved | JEFFREY CORPUZ |
| PLUMBING-Rough | 11/2/2020 | Partial Approval | JEFFREY CORPUZ |
| Footing/Foundation/Slab | 11/5/2020 | Approved | JEFFREY CORPUZ |
| Sewer | 11/5/2020 | Approved | JEFFREY CORPUZ |
| BUILDING-Rough-Frame | 11/16/2020 | Not Ready for Inspection | JEFFREY CORPUZ |
| Green Building Rough | 11/16/2020 | Not Ready for Inspection | JEFFREY CORPUZ |
| BUILDING-Rough-Frame | 11/23/2020 | Approved | JEFFREY CORPUZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Approved | JEFFREY CORPUZ |
| Green Building Rough | 11/23/2020 | Approved | JEFFREY CORPUZ |
| ELECTRICAL-Rough | 11/30/2020 | Approved | JEFFREY CORPUZ |
| PLUMBING-Rough | 11/30/2020 | Approved | JEFFREY CORPUZ |
| HVAC-Rough | 12/1/2020 | Approved | JEFFREY CORPUZ |
| Insulation | 12/1/2020 | Approved | JEFFREY CORPUZ |
| Drywall Nailing | 12/3/2020 | Approved | JEFFREY CORPUZ |
| Interior/Exterior Lathing | 12/3/2020 | Approved | JEFFREY CORPUZ |
| Final | 1/25/2021 | Partial Approval | JEFFREY CORPUZ |
| Green Building Final | 1/25/2021 | Approved | JEFFREY CORPUZ |
| SGSOV-Seismic Gas S/O Valve | 1/25/2021 | SGSOV Approved | JEFFREY CORPUZ |
| Smoke Detectors | 1/25/2021 | Approved | JEFFREY CORPUZ |