2214 W OAK GLEN PL 90039
Certificate Information: 2214 W OAK GLEN PL 90039
- Application / Permit
- 20014-10000-03294
- Plan Check / Job No.
- B20LA13917
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY BEDROOM AND BATHROOM ADDITION TO SFD PER WFPP.
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- CofO Issued on 3/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | SINA KHOSRAVI |
| Corrections Issued | 8/6/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/22/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 12/8/2020 | ZAW HAN |
| Applicant returned to address corrections | 2/1/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/8/2021 | AUNG SOE |
| Plan Check Approved | 6/15/2021 | SHANGQIN XIE |
| Issued | 6/29/2021 | APPLICANT |
| Building Plans Picked Up | 6/30/2021 | APPLICANT |
| CofO in Progress | 3/21/2022 | THOMAS LOGRASSO |
| Permit Finaled | 3/22/2022 | DEROLD HAUFF |
| CofO Issued | 3/22/2022 | DEROLD HAUFF |
| Permit Finaled | 3/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/2/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 2/12/2021 | KIRK LINKLATER |
| Tenant Habitability Plan | Cleared | 4/7/2021 | RICHARD BRINSON |
| Certificate of Compliance | Cleared | 4/29/2021 | RUBEN VASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/4/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/6/2021 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/10/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/25/2021 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/25/2021 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 8/30/2021 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/18/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 10/18/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 10/18/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 10/18/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/18/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/21/2021 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 10/21/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/21/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/4/2021 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 11/4/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/8/2021 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/8/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/8/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/10/2021 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 11/22/2021 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 12/15/2021 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 12/15/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/15/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/22/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 1/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/11/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 1/11/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/7/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| Final | 3/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/7/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 3/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 3/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Final | 3/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 3/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/7/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 3/7/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/10/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 3/10/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Final | 3/10/2022 | Approved | THOMAS LOGRASSO |
| Final | 3/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 3/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 3/14/2022 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 3/14/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 3/18/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 3/18/2022 | Approved | THOMAS LOGRASSO |