3917-3919 S VAN NESS AVE 90062

Certificate Information: 3917-3919 S VAN NESS AVE 90062

Application / Permit
20014-10000-03281
Plan Check / Job No.
B20LA13827
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION TO DUPLEX BUILDING TO EXTEND A BEDROOM AND RELOCATE A BATHROOM IN ONE UNIT
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2020 APPLICANT
Assigned to Plan Check Engineer 8/5/2020 SINA KHOSRAVI
Corrections Issued 8/5/2020 SINA KHOSRAVI
Plan Check Approved 9/11/2020 RICARDO RAMIREZ
Issued 9/24/2020 APPLICANT
Building Plans Picked Up 9/25/2020 APPLICANT
CofO in Progress 3/26/2021 DAVID FEILER
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/21/2020 ELAINE LEI
Sewer availability Cleared 8/21/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 8/25/2020 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2020 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/19/2020 Approved DAVID FEILER
PLUMBING-Rough 10/29/2020 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 11/2/2020 Partial Approval DAVID FEILER
PLUMBING-Rough 11/2/2020 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 11/10/2020 Partial Approval DAVID FEILER
ELECTRICAL-Rough 11/10/2020 Approved DAVID FEILER
Green Building Rough 11/10/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 11/10/2020 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 11/17/2020 Approved DAVID FEILER
Green Building Rough 11/17/2020 Approved DAVID FEILER
Interior/Exterior Lathing 11/17/2020 Partial Approval DAVID FEILER
PLUMBING-Rough 11/17/2020 Approved DAVID FEILER
Drywall Nailing 11/24/2020 Approved DAVID FEILER
Final 12/17/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 12/17/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 12/17/2020 Corrections Issued FREDDIE RIVERA
Final 3/25/2021 OK to Issue CofO DAVID FEILER
Green Building Final 3/25/2021 Approved DAVID FEILER
Smoke Detectors 3/25/2021 Approved DAVID FEILER