6122 W MELVIL ST 90034
Certificate Information: 6122 W MELVIL ST 90034
- Application / Permit
- 20014-10000-03244
- Plan Check / Job No.
- B20LA13684
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2 STORY ADDITION TO EXISTING 2 STORY DUPLEX
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Current Status
- Issued on 2/18/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | STARR CHEN |
| Corrections Issued | 10/16/2020 | STARR CHEN |
| Quality Review Completed | 10/29/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/25/2021 | STARR CHEN |
| Plan Check Approved | 5/20/2021 | STARR CHEN |
| Issued | 7/7/2021 | APPLICANT |
| Building Plans Picked Up | 7/9/2021 | APPLICANT |
| CofO in Progress | 2/8/2022 | EVAN COOPER |
| No Progress | 2/18/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/18/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | JEANIE LAM |
| Address approval | Cleared | 4/19/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/19/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Liu,, Hue Cam; Lic. No.: C66754 | 10732 LA BATISTA AVENUE FOUNTAIN VALLEY, CA 92708 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/30/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/3/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/18/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Corrections Issued | EVAN COOPER |
| Pre-Inspection | 10/19/2021 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/2/2021 | Approved | EVAN COOPER |
| Pre-Inspection | 11/2/2021 | Approved | EVAN COOPER |
| Rough-Elec/Plmb/HVAC | 11/2/2021 | Approved | EVAN COOPER |
| Insulation | 11/9/2021 | Approved | EVAN COOPER |
| Pre-Inspection | 11/16/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/28/2021 | Approved | EVAN COOPER |
| Final | 12/28/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/28/2021 | Approved | EVAN COOPER |
| Green Building Rough | 12/28/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/28/2021 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/28/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/11/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 2/8/2022 | Approved | EVAN COOPER |
| Final | 2/8/2022 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 2/8/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/8/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Approved | EVAN COOPER |
| Special/Order Compliance | 2/23/2022 | Corrections Issued | EVAN COOPER |