415 N WALKER AVE 90732
Certificate Information: 415 N WALKER AVE 90732
- Application / Permit
- 20014-10000-03234
- Plan Check / Job No.
- B20LA13628
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE REAR OF (E) SFD.
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/11/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/4/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 11/25/2020 | AMIR DANAI |
| Building Plans Picked Up | 11/25/2020 | APPLICANT |
| Issued | 1/29/2021 | APPLICANT |
| CofO in Progress | 6/13/2022 | ANSON MAGLASANG |
| Permit Finaled | 6/14/2022 | DEROLD HAUFF |
| CofO Issued | 6/14/2022 | DEROLD HAUFF |
| Permit Finaled | 6/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/23/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 10/13/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | New West; Lic. No.: 452943-B | 716 RITA REDONDO BEACH, CA 90277 |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/26/2021 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 4/6/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/19/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/24/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 5/27/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 5/27/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/27/2021 | Approved | JOHN KLARIN |
| Insulation | 7/19/2021 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 7/28/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 7/28/2021 | Approved | JOHN KLARIN |
| Gas Test | 2/25/2022 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | ANSON MAGLASANG |
| Final | 5/17/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Not Ready | ANSON MAGLASANG |
| Service/Power Release | 5/17/2022 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 5/17/2022 | Approved | ANSON MAGLASANG |
| Final | 6/10/2022 | OK to Issue CofO | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | ANSON MAGLASANG |