4847 N GENEVIEVE AVE 90041

Certificate Information: 4847 N GENEVIEVE AVE 90041

Application / Permit
20014-10000-03217
Plan Check / Job No.
B20LA13559
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
112 SQFT ADDITION TO (E) S.F.D AND INTERIOR AND EXTERIOR REMODEL REMODEL. WORK INCLUDES REMODEL KITCHEN, BEDROOM, BATHROOM, EXTERIOR WALLS, DOOR AND WINDOW CHANGE OUTS. STRUCTURAL DESIGN BY ENGINEER
Permit Issued
Issued on 12/4/2020
Issuing Office
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/3/2020 RACHEL BEYENE
Corrections Issued 8/5/2020 RACHEL BEYENE
Applicant returned to address corrections 9/2/2020 AMIR DANAI
Plan Check Approved 10/15/2020 ADAM HEGAZI
Building Plans Picked Up 10/26/2020 APPLICANT
Plan Check Approved 11/6/2020 GEORGE ALVAREZ
Issued 12/4/2020 APPLICANT
CofO in Progress 9/24/2021 BRAD BESCOS
Permit Finaled 9/29/2021 DEROLD HAUFF
CofO Issued 9/29/2021 DEROLD HAUFF
Permit Finaled 9/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/27/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 8/27/2020 CELINA MORENO
Sewer availability Cleared 8/27/2020 CELINA MORENO
Grading Pre-Inspection Cleared 9/14/2020 KIRK LINKLATER

Contact Information

Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2021 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 1/29/2021 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/1/2021 Approved CRAIG VAUGHAN
Insulation 2/18/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 2/22/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 2/22/2021 Not Ready for Inspection CRAIG VAUGHAN
Insulation 2/22/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/2/2021 No Access for Inspection CRAIG VAUGHAN
Green Building Rough 3/2/2021 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/8/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 3/8/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/8/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 3/12/2021 Approved CRAIG VAUGHAN
HVAC-Rough 3/12/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/12/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/15/2021 Approved CRAIG VAUGHAN
Green Building Rough 3/15/2021 Approved CRAIG VAUGHAN
HVAC-Rough 3/15/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/15/2021 Approved CRAIG VAUGHAN
Insulation 3/19/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/19/2021 Partial Approval CRAIG VAUGHAN
Drywall Nailing 3/25/2021 Approved RICHARD STEINBACH
Final 7/12/2021 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/12/2021 Approved CRAIG VAUGHAN
Green Building Final 7/12/2021 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 7/12/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 7/29/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 7/29/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 7/29/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 7/29/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/29/2021 Approved CRAIG VAUGHAN
Final 8/5/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/5/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 8/12/2021 Partial Inspection CRAIG VAUGHAN
Gas Test 8/12/2021 Approved CRAIG VAUGHAN
Green Building Final 8/12/2021 Corrections Issued CRAIG VAUGHAN
Final 9/15/2021 Conditional Approval CRAIG VAUGHAN
Green Building Final 9/15/2021 Approved CRAIG VAUGHAN
Final 9/23/2021 OK to Issue CofO BRAD BESCOS