8001 S GEORGETOWN AVE 90045
Certificate Information: 8001 S GEORGETOWN AVE 90045
- Application / Permit
- 20014-10000-03207
- Plan Check / Job No.
- B20LA13529
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 124 SQFT TO CREATE EXTEND LIVING ROOM, LAUNDRY AND BATH
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | ADAM HEGAZI |
| Corrections Issued | 8/5/2020 | ADAM HEGAZI |
| Building Plans Picked Up | 8/7/2020 | APPLICANT |
| Applicant returned to address corrections | 10/13/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 9/23/2022 | MINA HABILI |
| Applicant returned to address corrections | 3/23/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 3/30/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/5/2023 | EDWIN ESPIN |
| Plan Check Approved | 5/12/2023 | AMY GUEVARRA |
| Issued | 5/12/2023 | APPLICANT |
| CofO in Progress | 8/16/2024 | BOBBY KEY |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
| CofO Issued | 8/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | DINAH GARIN |
| ZA Case | Cleared | 5/9/2023 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2023 | Partial Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/29/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 10/12/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 10/12/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 10/24/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 10/25/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 10/25/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/25/2023 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 10/30/2023 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 11/1/2023 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 11/6/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Approved | BOBBY KEY |
| Insulation | 11/6/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 11/21/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/21/2023 | Partial Approval | BOBBY KEY |
| Insulation | 11/28/2023 | Approved | BOBBY KEY |
| Shower Pan | 11/28/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/1/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 12/11/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 5/2/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/2/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/10/2024 | Approved | BOBBY KEY |
| Service/Power Release | 5/10/2024 | Approved | BOBBY KEY |
| Final | 6/24/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 6/24/2024 | Approved | BOBBY KEY |
| HVAC-Final | 6/24/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/24/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/24/2024 | Approved | BOBBY KEY |
| Final | 8/16/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Approved | BOBBY KEY |