632 W 111TH ST 90044
Certificate Information: 632 W 111TH ST 90044
- Application / Permit
- 20014-10000-03203
- Plan Check / Job No.
- B20LA13510
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR RENOVATION, BEDROOM ADDITION TOTAL SQFT ADDITION IS 117 SQFT.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2020 | ADAM HEGAZI |
| Corrections Issued | 8/3/2020 | ADAM HEGAZI |
| Plan Check Approved | 9/15/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 12/14/2022 | JAMES CHAVEZ |
| Permit Finaled | 2/10/2023 | ANSON MAGLASANG |
| CofO Issued | 2/10/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/10/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/26/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 8/27/2020 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/19/2020 | Partial Approval | EUGENE CASSIDY |
| Special/Order Compliance | 10/19/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/22/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 11/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Deputy Wood Construction | 12/1/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 12/7/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 12/7/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/30/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/30/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/14/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 4/14/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 6/16/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 6/16/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 6/16/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/22/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 6/22/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 6/22/2021 | Partial Approval | JOHN KLARIN |
| PLUMBING-Rough | 6/22/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 7/2/2021 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 7/15/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/15/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/15/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/15/2021 | Approved | JOHN KLARIN |
| Final | 3/2/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 3/2/2022 | Approved | JOHN KLARIN |
| Green Building Final | 3/2/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 3/2/2022 | Approved | JOHN KLARIN |
| Final | 5/9/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Grading Pre-Inspection | 5/9/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 5/9/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 6/22/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/22/2022 | Approved | JOHN KLARIN |
| Final | 7/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 7/19/2022 | Corrections Issued | JOHN KLARIN |
| Final | 9/8/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/6/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 10/19/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 12/5/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 12/13/2022 | OK to Issue CofO | JAMES CHAVEZ |