9805 W CRAIGMITCHELL LANE 91040
Certificate Information: 9805 W CRAIGMITCHELL LANE 91040
- Application / Permit
- 20014-10000-03161
- Plan Check / Job No.
- B20LA13286
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING. ENLARGE MASTER BEDROOM, BATH ROOM AND CLOSET. EXTEND EXISTING GARAGE, LIVING, KITCHEN AND ADD A POOL BATHROOM.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- Issued on 6/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | RICARDO RAMIREZ |
| Corrections Issued | 7/30/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/9/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 12/22/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 6/7/2021 | SHANGQIN XIE |
| Issued | 6/22/2021 | APPLICANT |
| Building Plans Picked Up | 6/28/2021 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 8/11/2020 | MAXFIELD VERMY |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 8/20/2020 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 8/20/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/7/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 12/4/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/9/2020 | GABRIEL ROBLES |
| Specific Plan | Cleared | 5/6/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 5/6/2021 | MIGUEL GAMBOA |
| GPI Written Notices | Cleared | 6/7/2021 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 6/7/2021 | RICARDO RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/20/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/20/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/26/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/26/2021 | Approved | MATTHEW NELSON |
| Piling/Pier/Caisson | 7/26/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 8/4/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 8/16/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 8/18/2021 | Partial Approval | WILLIAM KUEHN |
| Deputy Drilled-In Anchors | 8/19/2021 | Conditional Approval | DAVID MATSON |
| Insulation | 8/19/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 8/19/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Wood Frame | 8/19/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Gas Test | 8/26/2021 | Approved | MATTHEW NELSON |
| Insulation | 8/26/2021 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 8/26/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 11/4/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/9/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 12/9/2021 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 12/9/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/9/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 12/9/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 12/9/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 12/10/2021 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 12/10/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 12/10/2021 | Approved | WILLIAM KUEHN |
| Insulation | 12/17/2021 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 12/23/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/23/2021 | Approved | WILLIAM KUEHN |
| Service/Power Release | 2/22/2022 | Corrections Issued | MATTHEW NELSON |
| Gas Test | 2/28/2022 | Approved | MATTHEW NELSON |
| Enclosure/Fence | 4/15/2022 | Partial Inspection | MATTHEW NELSON |
| Enclosure/Fence | 5/9/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 5/25/2022 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/25/2022 | Approved | MATTHEW NELSON |