923 1/2 S STANLEY AVE 90036

Certificate Information: 923 1/2 S STANLEY AVE 90036

Application / Permit
20014-10000-03147
Plan Check / Job No.
B20LA13213
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO (N) ADU WITH 2ND FLOOR ADDITION.
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 1/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 DANIEL YIP
Corrections Issued 8/26/2020 DANIEL YIP
Quality Review Completed 10/9/2020 HERNAN ARREOLA
Plan Check Approved 11/18/2020 DANIEL YIP
Issued 1/26/2021 APPLICANT
Building Plans Picked Up 6/30/2021 APPLICANT
CofO in Progress 1/4/2023 RICHARD DOCKUS
CofO Issued 1/13/2023 DEROLD HAUFF
Permit Finaled 1/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 10/9/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/13/2020 ELAINE LEI
Construction near power lines Cleared 10/16/2020 OSCAR CASTRO
Sewer availability Cleared 10/16/2020 ELAINE LEI
HPOZ Cleared 10/28/2020 CHRISTINA PARK

Contact Information

Contractor Whitaker Construction; Lic. No.: 804990-B P O BOX 1186      LOS ANGELES, CA 90078

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/11/2021 Corrections Issued JOSEPH MCGARRY
METHANE-Barrier 2/11/2021 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 2/11/2021 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 3/19/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 3/19/2021 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 3/19/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 4/8/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 4/8/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 4/8/2021 Partial Approval JOSEPH MCGARRY
Service/Power Release 7/9/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/22/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/22/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 9/22/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 9/22/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 9/22/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 9/22/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/13/2021 Approved ARTHUR SARGSYAN
Insulation 12/7/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 12/20/2021 Approved ARTHUR SARGSYAN
Green Building Rough 12/20/2021 Approved ARTHUR SARGSYAN
Shower Pan 2/24/2022 Approved ARTHUR SARGSYAN
Sewer 3/31/2022 Corrections Issued CRAIG DAVIS
Sewer 4/7/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 4/21/2022 Approved ARTHUR SARGSYAN
Pre-Inspection 7/12/2022 Approved ADAM ESCOTO
PLUMBING-Final 7/18/2022 Approved ADAM ESCOTO
Service/Power Release 8/3/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 10/6/2022 Approved JEFFREY MEAD
PLUMBING-Rough 11/10/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/27/2022 Approved JEFFREY MEAD
Final 12/27/2022 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 12/27/2022 Approved JEFFREY MEAD
Green Building Final 12/27/2022 Approved JEFFREY MEAD
METHANE-Final 12/27/2022 Approved JEFFREY MEAD
METHANE-Rough 12/27/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 12/27/2022 Approved JEFFREY MEAD
Final 1/3/2023 OK to Issue CofO RICHARD DOCKUS