11113 N EL DORADO AVE 91331

Certificate Information: 11113 N EL DORADO AVE 91331

Application / Permit
20014-10000-03145
Plan Check / Job No.
B20LA13209
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING PER WFPP.
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
CofO Issued on 7/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2020 APPLICANT
Assigned to Plan Check Engineer 8/12/2020 FERNANDO FLORES
Corrections Issued 8/12/2020 FERNANDO FLORES
Applicant returned to address corrections 6/2/2021 CRISTINA SALAZAR
Plan Check Approved 10/29/2021 RAHEL BEYENE
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 12/29/2021 APPLICANT
CofO in Progress 7/11/2023 MICHEL ABAJAN
Permit Finaled 7/12/2023 RONALD MYRICK
CofO Issued 7/12/2023 RONALD MYRICK
Permit Finaled 7/12/2023 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/21/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/22/2020 GUILLERMO PETRA
Sewer availability Cleared 10/22/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 7/15/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 7/15/2022 Partial Approval MICHEL ABAJAN
Sewer 7/15/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 7/26/2022 Corrections Issued DAVID MATSON
METHANE-Barrier 7/26/2022 Approved DAVID MATSON
Excavation/Setback/Form/Re-Bar 7/27/2022 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 7/29/2022 Approved MICHEL ABAJAN
Pre-Inspection 9/27/2022 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/26/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/26/2022 Approved MICHEL ABAJAN
Green Building Rough 10/26/2022 Approved MICHEL ABAJAN
HVAC-Rough 10/26/2022 Approved MICHEL ABAJAN
MERV13>=Rough 10/26/2022 Approved MICHEL ABAJAN
METHANE-Rough 10/26/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/26/2022 Approved MICHEL ABAJAN
Insulation 11/9/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/9/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 11/14/2022 Approved MICHEL ABAJAN
Shower Pan 11/23/2022 Approved MICHEL ABAJAN
Shower Pan 12/5/2022 Approved MICHEL ABAJAN
Shower Pan 12/7/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/27/2022 Corrections Issued MICHEL ABAJAN
Final 12/27/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 12/27/2022 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 12/27/2022 Corrections Issued MICHEL ABAJAN
MERV13>=Final 12/27/2022 Approved MICHEL ABAJAN
PLUMBING-Final 12/27/2022 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 12/27/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/13/2023 Approved MICHEL ABAJAN
Final 1/13/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 1/13/2023 Approved MICHEL ABAJAN
HVAC-Final 1/13/2023 Approved MICHEL ABAJAN
PLUMBING-Final 1/13/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready MICHEL ABAJAN
Final 1/25/2023 No Access for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Not Ready MATTHEW NELSON
Final 2/6/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready MICHEL ABAJAN
Final 7/11/2023 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Approved MICHEL ABAJAN