1249 S MUIRFIELD ROAD 90019
Certificate Information: 1249 S MUIRFIELD ROAD 90019
- Application / Permit
- 20014-10000-03142
- Plan Check / Job No.
- B20LA13195
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED 1-STORY ADDITION (415 SQFT) TO EXISTING DUPLEX TO CREATE TO EXTEND (E) BEDROOM AND CREATE KITCHEN. SCOPE OF WORK WILL ALSO INCLUDE AN INTERIOR REMODEL TO EXISTING UNITS. ***SHALL BE SPRINKLERED PER NFPA 13 D*** 1 OF 2
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 3/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | MICHAEL LOPEZ |
| Corrections Issued | 9/3/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 9/14/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 3/23/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 5/6/2021 | MICHAEL LOPEZ |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 11/23/2022 | STUART CHAPMAN |
| Permit Finaled | 3/19/2023 | DEROLD HAUFF |
| CofO Issued | 3/19/2023 | DEROLD HAUFF |
| Permit Finaled | 3/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2020 | ELAINE LEI |
| Tenant Habitability Plan | Cleared | 10/6/2020 | MICHAEL GREGERSON |
| Flood clearance | Cleared | 11/17/2020 | RAYMOND LAM |
| Low Impact Development | Cleared | 2/18/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/22/2021 | ROSA SILVA |
Contact Information
| Contractor | Primary Construction & Development Inc; Lic. No.: 1035793-B | 3925 CHEVY CHASE DR LA CANADA FLINTRIDGE, CA 91011 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2021 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Corrections Issued | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/16/2021 | Approved | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 6/18/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Drilled-In Anchors | 8/17/2021 | Conditional Approval | CALEB MEISTER |
| Deputy Wood Construction | 8/17/2021 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/19/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/19/2021 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 11/19/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/19/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 11/19/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Rough | 11/19/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/22/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/15/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 12/15/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 12/15/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 2/18/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 2/18/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/8/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 9/9/2022 | Approved | STUART CHAPMAN |
| Final | 9/9/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/9/2022 | Approved | STUART CHAPMAN |
| Green Building Final | 9/9/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 9/9/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 9/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 9/9/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 9/9/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 9/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 9/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 9/15/2022 | Approved | STUART CHAPMAN |
| Final | 9/15/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 9/15/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 9/15/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 10/3/2022 | Approved | STUART CHAPMAN |
| Final | 11/22/2022 | OK to Issue CofO | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 11/22/2022 | Approved | STUART CHAPMAN |