3505 N MARGUERITE ST 90065
Certificate Information: 3505 N MARGUERITE ST 90065
- Application / Permit
- 20014-10000-03121
- Plan Check / Job No.
- B20LA13156
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 Bedroom addition to (E) SFD
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Current Status
- CofO Issued on 10/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | HERNAN ARREOLA |
| Corrections Issued | 9/9/2020 | HERNAN ARREOLA |
| Quality Review Completed | 9/14/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 9/16/2020 | APPLICANT |
| Applicant returned to address corrections | 6/3/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/13/2023 | HERNAN ARREOLA |
| Plan Check Approved | 2/9/2023 | HERNAN ARREOLA |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 10/29/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 10/30/2025 | DEROLD HAUFF |
| CofO Issued | 10/30/2025 | DEROLD HAUFF |
| Permit Finaled | 10/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/16/2022 | STEVE MELGAR |
| Supp. Use District POD/CDO/TDO | Cleared | 7/8/2022 | NASHYA JENSEN |
| ZI | Cleared | 7/8/2022 | NASHYA JENSEN |
| Hydrant and Access approval | Cleared | 7/27/2022 | KURT CORRAL |
Contact Information
| Contractor | Grid Alternatives; Lic. No.: 867533-B | 1171 OCEAN AVE OAKLAND, CA 94608 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2023 | Corrections Issued | SCOTT FINNILA |
| Pre-Inspection | 5/8/2023 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 5/9/2023 | Corrections Issued | SCOTT FINNILA |
| Pre-Inspection | 7/20/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/16/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/26/2023 | Partial Inspection | AMY COLIN |
| Deputy Drilled-In Anchors | 3/20/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 4/1/2025 | Partial Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 5/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Wood Frame | 5/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/2/2025 | Approved | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 6/2/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 6/24/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/24/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 7/11/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 7/11/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | NICHOLAS LOPEZ |
| Final | 9/8/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 9/8/2025 | Approved | NICHOLAS LOPEZ |
| MERV13>=Final | 9/8/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| MERV13>=Rough | 9/8/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 9/8/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 9/16/2025 | Corrections Issued | NICHOLAS LOPEZ |
| MERV13>=Final | 9/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 9/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 9/30/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Special/Order Compliance | 10/22/2025 | Partial Inspection | NICHOLAS LOPEZ |
| Final | 10/28/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| MERV13>=Final | 10/28/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/28/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 10/28/2025 | Approved | NICHOLAS LOPEZ |