1036 S RIDGELEY DR 90019

Certificate Information: 1036 S RIDGELEY DR 90019

Application / Permit
20014-10000-03090
Plan Check / Job No.
B20LA13068
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR ADDITION (13'-6"x36'-0") AT REAR OF EXISTING SINGLE FAMILY DWELLING WITH INTERIOR REMODEL.
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
CofO Issued on 8/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 GEORGE ALVAREZ
Corrections Issued 7/31/2020 GEORGE ALVAREZ
Applicant returned to address corrections 9/23/2020 LUKE GONZALES
Applicant returned to address corrections 10/27/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 10/29/2020 FARSHAD ALIMOHAMADI
Issued 12/2/2020 APPLICANT
Building Plans Picked Up 12/7/2020 APPLICANT
CofO in Progress 7/13/2021 JOSEPH MCGARRY
Permit Finaled 8/14/2021 DEROLD HAUFF
CofO Issued 8/14/2021 DEROLD HAUFF
Permit Finaled 8/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/23/2020 THOMAS LANG
Sewer availability Cleared 9/23/2020 THOMAS LANG
HPOZ Cleared 10/15/2020 CHRISTINA PARK
Eng Process Fee Ord 176,300 Cleared 10/16/2020 PAMELA TENEZA

Contact Information

Contractor Arrowhead Remodeling & Design Inc; Lic. No.: 935108-B 18345 VENTURA BLVD #212      TARZANA, CA 91356
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/7/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 1/7/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 1/7/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Partial Approval STUART CHAPMAN
Green Building Rough 1/21/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 1/21/2021 Approved STUART CHAPMAN
Insulation 1/25/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval JOSEPH MCGARRY
Green Building Rough 1/27/2021 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 2/12/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/19/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 2/19/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Deputy Wood Construction 2/25/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 2/26/2021 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 2/26/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/26/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/15/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/15/2021 Approved JOSEPH MCGARRY
Green Building Rough 3/15/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/15/2021 Approved JOSEPH MCGARRY
Deputy Wood Construction 3/23/2021 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/24/2021 Approved JOSEPH MCGARRY
Green Building Rough 3/24/2021 Approved JOSEPH MCGARRY
HVAC-Rough 3/24/2021 Approved JOSEPH MCGARRY
Insulation 3/24/2021 Approved JOSEPH MCGARRY
Drywall Nailing 4/5/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/5/2021 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 4/5/2021 Approved CHRISTOPHER DELLEFIELD
Final 6/24/2021 OK to Issue CofO JOSEPH MCGARRY
Footing/Foundation/Slab 6/24/2021 Approved JOSEPH MCGARRY
Green Building Final 6/24/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 6/24/2021 Approved JOSEPH MCGARRY