532 S BERNAL AVE 90063
Certificate Information: 532 S BERNAL AVE 90063
- Application / Permit
- 20014-10000-03084
- Plan Check / Job No.
- B20LA13039
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- 15'X18'-6" ADDITION TO AN EXISTING 15'X15' STORAGE BLDG. All WORK PER WFPP
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofO Issued on 2/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | AMIR DANAI |
| Corrections Issued | 7/30/2020 | AMIR DANAI |
| Applicant returned to address corrections | 9/12/2020 | AUNG SOE |
| Plan Check Approved | 10/8/2020 | JESSE JIMENEZ |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Issued | 10/14/2020 | APPLICANT |
| CofO in Progress | 2/9/2022 | ADAM ESCOTO |
| Permit Finaled | 2/16/2022 | DEROLD HAUFF |
| CofO Issued | 2/16/2022 | DEROLD HAUFF |
| Permit Finaled | 2/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/14/2020 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2020 | PAMELA TENEZA |
| Grading Pre-Inspection | Cleared | 10/6/2020 | AMIR DANAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/10/2020 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 12/4/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 1/4/2021 | Corrections Issued | ROBERT VORHIS |
| Wood Frame | 1/4/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 1/13/2021 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/6/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 4/6/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 4/6/2021 | Approved | ROBERT VORHIS |
| Drywall Nailing | 6/21/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 7/29/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 7/29/2021 | Approved | ROBERT VORHIS |
| Smoke Detectors | 7/29/2021 | Approved | ROBERT VORHIS |
| Final | 8/25/2021 | Conditional Approval | ROBERT VORHIS |
| ELECTRICAL-Final | 2/9/2022 | Approved | ADAM ESCOTO |
| Final | 2/9/2022 | OK to Issue CofO | ADAM ESCOTO |
| HVAC-Final | 2/9/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 2/9/2022 | Approved | ADAM ESCOTO |