742 W 140TH ST 90247

Certificate Information: 742 W 140TH ST 90247

Application / Permit
20014-10000-03075
Plan Check / Job No.
B20LA12983
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (217 SF) TO EXISTING ONE STORY SFD AND INTERIOR REMODEL (RELOCATE KITCHEN, BEDROOM, NEW BATHROOM NEW WALKING CLOSET, NEW LAUNDRY RM FRAMING - ELECTRICAL - PLUMBING - HVAC)
Permit Issued
Issued on 9/23/2020
Issuing Office
Current Status
CofO Issued on 3/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/12/2020 TSE MING HUANG
Corrections Issued 8/12/2020 TSE MING HUANG
Plan Check Approved 9/17/2020 ADAM HEGAZI
Issued 9/23/2020 APPLICANT
Building Plans Picked Up 9/24/2020 APPLICANT
CofO in Progress 2/17/2021 EUGENE CASSIDY
Permit Finaled 3/15/2021 DEROLD HAUFF
CofO Issued 3/15/2021 DEROLD HAUFF
Permit Finaled 3/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/24/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 8/24/2020 ERIK BEASLEY
Sewer availability Cleared 8/24/2020 ERIK BEASLEY
Specific Plan Cleared 8/31/2020 KEVIN ARUCAN
CPC Cleared 9/1/2020 JOE LUCKEY
CPC Cleared 9/1/2020 JOE LUCKEY
Miscellaneous Cleared 9/1/2020 JOE LUCKEY
Supp. Use District POD/CDO/TDO Cleared 9/1/2020 JOE LUCKEY
ZA Case Cleared 9/1/2020 JOE LUCKEY
ZA Case Cleared 9/1/2020 JOE LUCKEY
ZA Case Cleared 9/1/2020 JOE LUCKEY
ZA Case Cleared 9/1/2020 JOE LUCKEY
Grading Pre-Inspection Cleared 9/8/2020 KIRK LINKLATER
GPI Written Notices Cleared 9/17/2020 TSE MING HUANG

Contact Information

Contractor Gwg Construction Inc; Lic. No.: 643695-B 1740 W 127TH STREET      LOS ANGELES, CA 90047
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2020 Approved EUGENE CASSIDY
METHANE-Barrier 10/5/2020 Approved EUGENE CASSIDY
METHANE-Subgrade 10/5/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/9/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 10/9/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 10/9/2020 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 10/9/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 10/9/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/15/2020 Partial Inspection EUGENE CASSIDY
HVAC-Rough 10/20/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 10/20/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/26/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 10/28/2020 Approved EUGENE CASSIDY
Green Building Rough 10/28/2020 Approved EUGENE CASSIDY
Insulation 10/28/2020 Approved EUGENE CASSIDY
MERV13>=Rough 10/28/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 11/9/2020 Approved EUGENE CASSIDY
Drywall Nailing 11/17/2020 Approved EUGENE CASSIDY
Shower Pan 12/9/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 12/10/2020 Approved JOSEPH MCGARRY
Final 2/1/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 2/1/2021 Corrections Issued EUGENE CASSIDY
MERV13>=Final 2/1/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/1/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 2/1/2021 Approved EUGENE CASSIDY
Pre-Inspection 2/4/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 2/17/2021 Approved EUGENE CASSIDY
Final 2/17/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 2/17/2021 Approved EUGENE CASSIDY
HVAC-Final 2/17/2021 Approved EUGENE CASSIDY
MERV13>=Final 2/17/2021 Approved EUGENE CASSIDY
PLUMBING-Final 2/17/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Approved EUGENE CASSIDY