3673 S SOMERSET DR 90016

Certificate Information: 3673 S SOMERSET DR 90016

Application / Permit
20014-10000-03057
Plan Check / Job No.
B20LA12883
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION (28' x 15'-11", 463 sf) WITH ENGINEER DESIGN
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 4/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/28/2020 TSE MING HUANG
Corrections Issued 7/28/2020 TSE MING HUANG
Plan Check Approved 8/28/2020 SAMUEL GONZALEZ
Issued 9/10/2020 APPLICANT
Building Plans Picked Up 9/16/2020 APPLICANT
CofO in Progress 4/1/2021 DAVID FEILER
Permit Finaled 4/16/2021 DEROLD HAUFF
CofO Issued 4/16/2021 DEROLD HAUFF
Permit Finaled 4/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/6/2020 CECILIO NAVARRO
Sewer availability Cleared 8/6/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/12/2020 CECILIO NAVARRO

Contact Information

Contractor N B K Construction; Lic. No.: 987864-B 16738 LAKESHORE DR #H40      LAKE ELSINORE, CA 92530
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2020 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 9/28/2020 Approved DAVID FEILER
Footing/Foundation/Slab 9/28/2020 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Partial Approval DAVID FEILER
PLUMBING-Rough 10/13/2020 Not Ready for Inspection DAVID FEILER
Underground Mechanical 10/14/2020 Not Ready for Inspection DAVID FEILER
HVAC-Rough 11/13/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 11/13/2020 Partial Approval DAVID FEILER
Underground Mechanical 11/13/2020 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 11/17/2020 Partial Inspection DAVID FEILER
Green Building Rough 11/17/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 11/17/2020 Partial Approval DAVID FEILER
ELECTRICAL-Rough 12/10/2020 Approved STUART CHAPMAN
HVAC-Rough 12/10/2020 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 12/11/2020 Approved STUART CHAPMAN
Wood Frame 12/11/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/15/2020 Approved DAVID FEILER
Green Building Rough 12/15/2020 Approved DAVID FEILER
HVAC-Rough 12/15/2020 Approved DAVID FEILER
Insulation 12/15/2020 Approved DAVID FEILER
Drywall Nailing 12/21/2020 Approved DAVID FEILER
Interior/Exterior Lathing 12/21/2020 Partial Approval DAVID FEILER
Shower Pan 1/7/2021 Approved STUART CHAPMAN
Gas Test 2/1/2021 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 2/1/2021 Approved DAVID FEILER
Final 3/24/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 3/24/2021 Approved DAVID FEILER
Green Building Final 3/24/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 3/24/2021 Approved DAVID FEILER
ELECTRICAL-Final 4/1/2021 Approved DAVID FEILER
Final 4/1/2021 OK to Issue CofO DAVID FEILER
HVAC-Final 4/1/2021 Approved DAVID FEILER
PLUMBING-Final 4/1/2021 Approved DAVID FEILER
Service/Power Release 4/1/2021 Approved DAVID FEILER