13000 W WELBY WAY 91606
Certificate Information: 13000 W WELBY WAY 91606
- Application / Permit
- 20014-10000-03016
- Plan Check / Job No.
- B20LA12677
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 125 SF ADDITION WITH MASTERBATH,CLOSET, LAUNDRY ROOM AND INTERIOR REMODEL OF EXISTING RESIDENCE: KITCHEN AND RESTROOM
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- Current Status
- CofO Issued on 12/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 7/24/2020 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 8/12/2020 | ZAW HAN |
| Plan Check Approved | 8/18/2020 | ZAW HAN |
| Issued | 8/27/2020 | APPLICANT |
| Building Plans Picked Up | 8/28/2020 | APPLICANT |
| CofO in Progress | 12/3/2020 | BRENDAN LOONEY |
| Permit Finaled | 12/25/2021 | MICHAEL SMITH |
| CofO Issued | 12/25/2021 | MICHAEL SMITH |
| Permit Finaled | 12/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/30/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/30/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Projekta Inc; Lic. No.: 1010761-B | 1215 N RED GUM STREET #F ANAHEIM, CA 92806 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28000 S WESTERN AVE UNIT 209 SAN PEDRO, CA 90732 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/2/2020 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/2/2020 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 9/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/24/2020 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/24/2020 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 9/24/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Insulation | 9/24/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/24/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/28/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 9/28/2020 | Approved | BRENDAN LOONEY |
| Insulation | 9/28/2020 | Approved | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 9/28/2020 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 10/2/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 10/5/2020 | Approved | DANIEL ORRANTE |
| Shower Pan | 10/5/2020 | Corrections Issued | DANIEL ORRANTE |
| Interior/Exterior Lathing | 10/7/2020 | Approved | BRENDAN LOONEY |
| Final | 11/17/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 11/17/2020 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 11/17/2020 | Approved | BRENDAN LOONEY |
| Final | 11/24/2020 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Not Ready | BRENDAN LOONEY |
| Final | 12/2/2020 | OK to Issue CofO | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Approved | BRENDAN LOONEY |