1830 W 65TH PL 90047
Certificate Information: 1830 W 65TH PL 90047
- Application / Permit
- 20014-10000-02987
- Plan Check / Job No.
- B20LA12528
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE REAR SFD TO CREATING A NEW MASTER BEDROOM AND BATHROOM.
- Permit Issued
- Issued on 9/25/2020
- Issuing Office
- Current Status
- CofO Issued on 2/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | TSE MING HUANG |
| Corrections Issued | 7/22/2020 | TSE MING HUANG |
| Plan Check Approved | 9/9/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 9/10/2020 | APPLICANT |
| Issued | 9/25/2020 | APPLICANT |
| CofO in Progress | 7/1/2021 | HORACE FULTZ |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
| CofO Issued | 2/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 7/24/2020 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 7/28/2020 | DALE WILLIAMS |
| Community Plan Implem. Overlay | Cleared | 7/29/2020 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 7/30/2020 | TAIMOUR TANAVOLI |
| Roof/Waste drainage to street | Cleared | 8/5/2020 | WALLIE JONG |
| Sewer availability | Cleared | 8/5/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | WALLIE JONG |
Contact Information
| Contractor | Paars Design & Build; Lic. No.: 998847-B | P O BOX 881504 LOS ANGELES, CA 90009 |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 10/20/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 10/26/2020 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/26/2020 | Approved | FREDDIE RIVERA |
| Insulation | 11/2/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | FREDDIE RIVERA |
| Insulation | 12/8/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/8/2020 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 12/8/2020 | Approved | FREDDIE RIVERA |
| Wood Frame | 12/8/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 12/24/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/24/2020 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/24/2020 | Approved | FREDDIE RIVERA |
| Final | 6/2/2021 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/2/2021 | Approved | FREDDIE RIVERA |