12538 W GREENE AVE 90066

Certificate Information: 12538 W GREENE AVE 90066

Application / Permit
20014-10000-02980
Plan Check / Job No.
B20LA12495
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF (E) 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 SINA KHOSRAVI
Corrections Issued 7/28/2020 SINA KHOSRAVI
Plan Check Approved 1/21/2021 SHANGQIN XIE
Issued 1/27/2022 APPLICANT
Building Plans Picked Up 2/16/2022 APPLICANT
CofO in Progress 8/25/2023 HERBERT GIRON
Permit Finaled 9/5/2023 DANIEL ORRANTE
CofO Issued 9/5/2023 DANIEL ORRANTE
Permit Finaled 9/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/18/2020 KATHLEEN LEE
Eng Process Fee Ord 176,300 Cleared 8/18/2020 KATHLEEN LEE
Sewer availability Cleared 8/24/2020 KATHLEEN LEE
Low Impact Development Cleared 1/7/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/12/2021 KATHLEEN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/3/2022 Corrections Issued RICHARD STEINBACH
PLUMBING-Rough 3/7/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/10/2022 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 3/10/2022 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 6/23/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 6/23/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/22/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 7/22/2022 Corrections Issued HERBERT GIRON
Green Building Rough 7/22/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 7/22/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 7/22/2022 Approved HERBERT GIRON
ELECTRICAL-Rough 7/26/2022 Approved HERBERT GIRON
HVAC-Rough 7/26/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/11/2022 Not Ready for Inspection HERBERT GIRON
Green Building Rough 8/11/2022 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 8/11/2022 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 8/15/2022 Corrections Issued HERBERT GIRON
Green Building Rough 8/15/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/15/2022 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 8/22/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/23/2022 Approved HERBERT GIRON
Insulation 8/23/2022 Approved HERBERT GIRON
Gas Test 8/29/2022 Corrections Issued HERBERT GIRON
Gas Test 8/31/2022 Approved HERBERT GIRON
Drywall Nailing 9/6/2022 Approved HERBERT GIRON
Shower Pan 9/12/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 9/20/2022 Approved HERBERT GIRON
Sewer 9/20/2022 Approved HERBERT GIRON
Special/Order Compliance 10/31/2022 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 5/30/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/30/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 5/30/2023 Approved HERBERT GIRON
ELECTRICAL-Final 7/26/2023 Approved HERBERT GIRON
Final 7/26/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 7/26/2023 Approved HERBERT GIRON
Green Building Final 7/26/2023 Approved HERBERT GIRON
HVAC-Final 7/26/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/26/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved HERBERT GIRON
Final 8/18/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/18/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/18/2023 Not Ready for Inspection HERBERT GIRON
Final 8/25/2023 OK to Issue CofO HERBERT GIRON
Gas Test 8/25/2023 Approved HERBERT GIRON
HVAC-Final 8/25/2023 Approved HERBERT GIRON
PLUMBING-Final 8/25/2023 Approved HERBERT GIRON