1960 W 104TH ST 90047
Certificate Information: 1960 W 104TH ST 90047
- Application / Permit
- 20014-10000-02979
- Plan Check / Job No.
- B20LA12493
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 26'6" X 12'10" ADDITION TO AND CONVERSION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE 186,481
- Permit Issued
- Issued on 10/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | SINA KHOSRAVI |
| Corrections Issued | 7/23/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/19/2021 | DANIEL YIP |
| Applicant returned to address corrections | 5/24/2021 | STANLEY RAAP |
| Plan Check Approved | 6/15/2021 | STANLEY RAAP |
| Issued | 10/30/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| CofO in Progress | 8/26/2022 | ENRIQUE MIRELES |
| CofO Issued | 12/14/2022 | DEROLD HAUFF |
| Permit Finaled | 12/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/1/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/20/2020 | JEANIE LAM |
| ZA Case | Cleared | 3/9/2021 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 4/26/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2022 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 3/15/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 3/15/2022 | Partial Approval | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 3/21/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/4/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 4/4/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Approved | HORACE FULTZ |
| Rough-Elec/Plmb/HVAC | 5/23/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 5/27/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 5/27/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/3/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/3/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/27/2022 | Corrections Issued | HORACE FULTZ |
| Shower Pan | 6/27/2022 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 7/2/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 7/5/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/29/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Gas Test | 7/29/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 7/29/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Sewer | 7/29/2022 | Approved | RYAN SALAZAR |
| Final | 8/18/2022 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/18/2022 | Approved | ENRIQUE MIRELES |
| Final | 8/25/2022 | OK to Issue CofO | ENRIQUE MIRELES |