680 N STONE CANYON ROAD 90077

Certificate Information: 680 N STONE CANYON ROAD 90077

Application / Permit
20014-10000-02974
Plan Check / Job No.
B20LA12474
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
296 SF 1-STORY ADDITION/REMODEL TO AN EXISTING 2-STORY SFD.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
Issued on 11/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 CHUNG-WEN CHUANG
Corrections Issued 8/24/2020 CHUNG-WEN CHUANG
Quality Review Completed 9/2/2020 KESETE HAREGOT
Plan Check Approved 11/10/2020 CHUNG-WEN CHUANG
Building Plans Picked Up 11/13/2020 APPLICANT
Issued 11/24/2020 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/30/2020 KIRK LINKLATER
Roof/Waste drainage to street Cleared 10/5/2020 DINAH GARIN
Sewer availability Cleared 10/5/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/6/2020 DINAH GARIN

Contact Information

Architect Peck,, Christopher M; Lic. No.: C27316 C.M. PECK CONSULTING   25 S. EL MOLINO AVE    PASADENA, CA 911012023
Contractor D K Building And Design; Lic. No.: 871345-B 25864 TURQUESA DR      VALENCIA, CA 91355
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/17/2020 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 12/21/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 12/22/2020 Partial Approval MATT KELLERMAN
FLOOD-Elevation Certificate 12/22/2020 Approved MATT KELLERMAN
Footing/Foundation/Slab 12/22/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 1/5/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/8/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 1/11/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/13/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/15/2021 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/2/2021 Approved CARLOS MATAMOROS
FLOOD-Proofing Certificate 3/2/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Approved CARLOS MATAMOROS
Structural Steel Frame 3/2/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 4/1/2021 Approved ANTHONY MCDOWALL
HVAC-Rough 4/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 4/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/9/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 4/13/2021 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 4/14/2021 Approved JESUS PINEDA
Special/Order Compliance 4/14/2021 Partial Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/8/2021 Approved CHRISTOPHER WILSON
Final 7/8/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 7/8/2021 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 7/8/2021 Corrections Issued CHRISTOPHER WILSON
Final 7/13/2021 Conditional Approval CHRISTOPHER WILSON
Smoke Detectors 7/13/2021 Approved CHRISTOPHER WILSON
Final 7/25/2024 Not Ready for Inspection CHRISTOPHER WILSON