680 N STONE CANYON ROAD 90077
Certificate Information: 680 N STONE CANYON ROAD 90077
- Application / Permit
- 20014-10000-02974
- Plan Check / Job No.
- B20LA12474
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 296 SF 1-STORY ADDITION/REMODEL TO AN EXISTING 2-STORY SFD.
- Permit Issued
- Issued on 11/24/2020
- Issuing Office
- Current Status
- Issued on 11/24/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 8/24/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 9/2/2020 | KESETE HAREGOT |
| Plan Check Approved | 11/10/2020 | CHUNG-WEN CHUANG |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| Issued | 11/24/2020 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/30/2020 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 10/5/2020 | DINAH GARIN |
| Sewer availability | Cleared | 10/5/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | DINAH GARIN |
Contact Information
| Architect | Peck,, Christopher M; Lic. No.: C27316 | C.M. PECK CONSULTING 25 S. EL MOLINO AVE PASADENA, CA 911012023 |
| Contractor | D K Building And Design; Lic. No.: 871345-B | 25864 TURQUESA DR VALENCIA, CA 91355 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/17/2020 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 12/21/2020 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Partial Approval | MATT KELLERMAN |
| FLOOD-Elevation Certificate | 12/22/2020 | Approved | MATT KELLERMAN |
| Footing/Foundation/Slab | 12/22/2020 | Partial Approval | MATT KELLERMAN |
| Deputy Reinf. Concrete | 1/5/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 1/8/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 1/11/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/13/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/15/2021 | Conditional Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/2/2021 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 3/2/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Approved | CARLOS MATAMOROS |
| Structural Steel Frame | 3/2/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/1/2021 | Approved | ANTHONY MCDOWALL |
| HVAC-Rough | 4/9/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 4/9/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 4/9/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 4/13/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Drywall Nailing | 4/14/2021 | Approved | JESUS PINEDA |
| Special/Order Compliance | 4/14/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/8/2021 | Approved | CHRISTOPHER WILSON |
| Final | 7/8/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/8/2021 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/8/2021 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 7/8/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 7/13/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Smoke Detectors | 7/13/2021 | Approved | CHRISTOPHER WILSON |
| Final | 7/25/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |