2519 1/2 W 18TH ST 90019
Certificate Information: 2519 1/2 W 18TH ST 90019
- Application / Permit
- 20014-10000-02973
- Plan Check / Job No.
- B20LA12464
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (5) Apartment
- Work Description
- NEW ATTACHED ADU ADDITION TO AN EXISTING DUPLEX PER LAMC 12.22.A33
- Permit Issued
- Issued on 3/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Green Plans Picked Up | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | MANUEL MONTUFAR |
| Corrections Issued | 8/14/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 8/20/2020 | RODOLFO ARIAS |
| Building Plans Picked Up | 8/25/2020 | APPLICANT |
| Applicant returned to address corrections | 4/28/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 5/4/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 5/10/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 9/2/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 9/15/2022 | MANUEL MONTUFAR |
| Plan Check Approved | 10/6/2022 | MANUEL MONTUFAR |
| Issued | 3/30/2023 | APPLICANT |
| CofO in Progress | 8/20/2025 | WILLIAM SIERRA |
| CofO in Progress | 8/20/2025 | WILLIAM SIERRA |
| CofO in Progress | 9/12/2025 | WILLIAM SIERRA |
| Permit Finaled | 9/19/2025 | DEROLD HAUFF |
| CofO Issued | 9/19/2025 | DEROLD HAUFF |
| Permit Finaled | 9/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/15/2022 | JEANIE LAM |
| Address approval | Cleared | 6/2/2022 | JEANIE LAM |
| Address approval | Cleared | 6/2/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 7/11/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | JEANIE LAM |
| Green Code | Cleared | 9/15/2022 | MANUEL MONTUFAR |
| Community Plan Implem. Overlay | Cleared | 9/27/2022 | KYLE WINSTON |
| ZI | Cleared | 9/27/2022 | KYLE WINSTON |
Contact Information
| Architect | Paik,, Chang Hak; Lic. No.: C37928 | 3131 FOOTHILL BLVD #L LA CRESCENTA, CA 91214 |
| Contractor | Evolution Building Contractor'S Inc; Lic. No.: 1012700-B | 9865 REDWOOD AVE HESPERIA, CA 92345 |
| Engineer | Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 | 4000 PARK NEWPORT SUITE 303 NEWPORT BEACH, CA 92660 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
| Geologist | Feucht,, Alex Thomas; Lic. No.: GEO4433 | 2443 EAGLE HARBOR DRIVE HENDERSON, NV 890527136 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Conditional Approval | DARRYL ARNOLD |
| Special/Order Compliance | 4/13/2023 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Barrier | 5/2/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 5/2/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 5/2/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Methane Barrier | 5/8/2023 | Approved | DONALD CRICHLOW |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/10/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 5/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Methane Barrier | 5/11/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| METHANE-Final | 5/15/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Partial Approval | STUART CHAPMAN |
| Special/Order Compliance | 8/23/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 9/8/2023 | Approved | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 9/8/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Not Ready for Inspection | ROY SPAULDING |
| Wood Frame | 11/1/2023 | Corrections Issued | DAVID FEILER |
| Wood Frame | 11/6/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Insulation | 11/14/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Wood Frame | 11/14/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/30/2023 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 7/16/2024 | Approved | JOSEPH MCGARRY |
| Final | 8/13/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Footing/Foundation/Slab | 8/13/2024 | Approved | WILLIAM SIERRA |
| Green Building Final | 8/13/2024 | Corrections Issued | WILLIAM SIERRA |
| METHANE-Barrier | 8/13/2024 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 8/13/2024 | Approved | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Smoke Detectors | 8/13/2024 | Approved | WILLIAM SIERRA |
| Structural Steel Frame | 8/13/2024 | Corrections Issued | WILLIAM SIERRA |
| Final | 8/23/2024 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 8/23/2024 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Structural Steel Frame | 8/23/2024 | Approved | WILLIAM SIERRA |
| Final | 9/4/2024 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 9/4/2024 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Approved | WILLIAM SIERRA |
| Special/Order Compliance | 9/6/2024 | Approved | WILLIAM SIERRA |
| Final | 7/21/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 7/21/2025 | Approved | WILLIAM SIERRA |
| Final | 7/24/2025 | Corrections Issued | LUIS CASTRO |
| Final | 8/19/2025 | Conditional Approval | WILLIAM SIERRA |
| Final | 8/20/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 9/12/2025 | OK to Issue CofO | WILLIAM SIERRA |