380 N MESA ROAD 90402
Certificate Information: 380 N MESA ROAD 90402
- Application / Permit
- 20014-10000-02972
- Plan Check / Job No.
- B20LA12458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 STORY ADDITION WITH BASEMENT GARAGE TO EXISTING 2 STORY SFD, SEE COMMENTS
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- Issued on 2/25/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | STARR CHEN |
| Corrections Issued | 8/8/2020 | STARR CHEN |
| Quality Review Completed | 8/31/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 9/3/2020 | APPLICANT |
| Applicant returned to address corrections | 10/21/2020 | STARR CHEN |
| Applicant returned to address corrections | 11/6/2020 | STARR CHEN |
| Applicant returned to address corrections | 2/3/2021 | STARR CHEN |
| Applicant returned to address corrections | 9/16/2021 | STARR CHEN |
| Applicant returned to address corrections | 11/9/2021 | STARR CHEN |
| Plan Check Approved | 11/29/2021 | STARR CHEN |
| Issued | 2/25/2022 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 7/31/2020 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 7/31/2020 | STARR CHEN |
| BHO/Hillside ordinance | Cleared | 9/11/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/11/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/11/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/11/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/11/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/11/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 12/18/2020 | YVAINNE GALSIM |
| Coastal Zone | Cleared | 12/23/2020 | RICHARD REASER |
| Roof/Waste drainage to street | Cleared | 1/14/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 2/9/2021 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 3/3/2021 | JOHN KIM |
Contact Information
| Architect | Prentice,, Scott Charles; Lic. No.: C23183 | PO BOX 518 PACIFIC PALISADES, CA 90272 |
| Contractor | Pacific Coast Environments; Lic. No.: 616213-B | 5425 E MEZZANINE WAY LONG BEACH, CA 90808 |
| Engineer | Miyamoto,, Yoshiaki Wayne; Lic. No.: L4825 | 4396 MENTONE AVE CULVER CITY, CA 90230 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 5/18/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 5/19/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 5/20/2022 | Conditional Approval | MICHAEL PELHAM |
| Pre-Inspection | 5/31/2022 | Partial Inspection | JOHN KIDWELL |
| Piling/Pier/Caisson | 6/2/2022 | Partial Approval | ANDREW NAVE |
| Deputy Drilled-In Anchors | 6/3/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/8/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/13/2022 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 6/15/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Grading | 7/7/2022 | Approved | MICHAEL PELHAM |
| Deputy Grading | 7/8/2022 | Approved | MICHAEL PELHAM |
| Deputy Grading | 7/11/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 7/13/2022 | No Access for Inspection | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 7/19/2022 | Partial Approval | ANDREW NAVE |
| Deputy Grading | 8/8/2022 | No Access for Inspection | KENNETH NAGLE |
| Deputy Grading | 8/9/2022 | No Access for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 8/18/2022 | Conditional Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 8/23/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2022 | Partial Inspection | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 9/20/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 10/6/2022 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/17/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 10/21/2022 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 10/24/2022 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/7/2022 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 11/10/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 12/22/2022 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/30/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/30/2022 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 2/2/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 2/16/2023 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 3/7/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 3/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/3/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/5/2023 | Approved | OGANES TARAKHCHYAN |
| Reinforced Concrete Frame | 7/18/2023 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/26/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/26/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/7/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/6/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/6/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/6/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 5/28/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 6/26/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/26/2024 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 7/1/2024 | Approved | ARAM AVEDISIAN |