4883 N AVOCA ST 90041
Certificate Information: 4883 N AVOCA ST 90041
- Application / Permit
- 20014-10000-02965
- Plan Check / Job No.
- B20LA12435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ROOM ADDITION ENTRY LIVING ROOM OF 70 SQ.FT., NEW ENTRY PORCH AND REMODEL OF FIRST FLOOR KITCHEN, 1/2 RESTROOM, LIVING ROOM, LAUNDRY ROOM AND 2ND FLOOR MASTER BEDROOM-MASTER BATHROOM AND 2 BEDROOM WITH RESTROOM. CONVERT EXISTING GARAGE TO ADU-STUDIO.
- Permit Issued
- Issued on 10/15/2020
- Issuing Office
- Current Status
- CofO Issued on 12/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | DANIEL YIP |
| Corrections Issued | 8/10/2020 | DANIEL YIP |
| Quality Review Completed | 8/31/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Plan Check Approved | 10/15/2020 | DANIEL YIP |
| Issued | 10/15/2020 | APPLICANT |
| CofO in Progress | 11/17/2021 | CRAIG VAUGHAN |
| Permit Finaled | 12/1/2021 | DEROLD HAUFF |
| CofO Issued | 12/1/2021 | DEROLD HAUFF |
| Permit Finaled | 12/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/17/2020 | PATRICK MISCHLICH |
| Address approval | Cleared | 9/18/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 9/18/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 9/18/2020 | RENZ SORIANO |
| GPI Written Notices | Cleared | 10/9/2020 | DANIEL YIP |
Contact Information
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/22/2020 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/22/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/26/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/28/2020 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 10/30/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 12/4/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/4/2020 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 12/4/2020 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/4/2020 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/2/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 2/2/2021 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 2/2/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 2/2/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 2/11/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/19/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/19/2021 | Approved | CRAIG VAUGHAN |
| Gas Test | 6/4/2021 | Approved | CRAIG VAUGHAN |
| Final | 9/3/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/3/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 9/3/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 9/3/2021 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 9/3/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/1/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 11/1/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/15/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/15/2021 | Conditional Approval | CRAIG VAUGHAN |
| Green Building Final | 11/15/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 11/15/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/15/2021 | Approved | CRAIG VAUGHAN |