7420 S MCCONNELL AVE adu 90045

Certificate Information: 7420 S MCCONNELL AVE adu 90045

Application / Permit
20014-10000-02964
Plan Check / Job No.
B20LA12425
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE. ADDITION WILL CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 3/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 MICHAEL LOPEZ
Corrections Issued 9/3/2020 MICHAEL LOPEZ
Quality Review Completed 9/14/2020 PRANITA SHAH
Applicant returned to address corrections 4/21/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/2/2021 MICHAEL LOPEZ
Plan Check Approved 7/2/2021 MICHAEL LOPEZ
Issued 2/18/2022 APPLICANT
Building Plans Picked Up 2/28/2022 APPLICANT
CofO in Progress 2/23/2024 BOBBY KEY
Permit Finaled 3/9/2024 DANIEL ORRANTE
CofO Issued 3/9/2024 DANIEL ORRANTE
Permit Finaled 3/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 10/19/2020 TERRI OSBORNE
ZA Case Cleared 10/19/2020 TERRI OSBORNE
Address approval Cleared 12/3/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 12/3/2020 SAUL GARCIA
Sewer availability Cleared 12/3/2020 SAUL GARCIA
Roof/Waste drainage to street Cleared 12/17/2020 SAUL GARCIA
Grading Pre-Inspection Cleared 2/5/2021 BRIAN MILLER
Specific Plan Cleared 2/16/2021 FREDDY GARCIA

Contact Information

Contractor M Vision Construction; Lic. No.: 1004743-B 5470 ALVERN CIR      LOS ANGELES, CA 90045
Engineer Samara,, Muzahim Ali; Lic. No.: C26015 9100 S SEPULVEDA BLVD SUITE 115      LOS ANGELES, CA 90045

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/20/2022 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 5/2/2022 Approved DAVID FEILER
METHANE-Barrier 5/2/2022 Approved DAVID FEILER
METHANE-Subgrade 5/2/2022 Approved DAVID FEILER
Deputy Reinf. Concrete 5/10/2022 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/29/2022 Partial Approval BOBBY KEY
Deputy Wood Construction 11/2/2022 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Approved BOBBY KEY
ELECTRICAL-Rough 1/13/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 1/20/2023 Approved BOBBY KEY
HVAC-Rough 1/20/2023 Approved BOBBY KEY
PLUMBING-Rough 1/20/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 2/1/2023 Not Ready for Inspection BOBBY KEY
Green Building Rough 2/1/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 2/1/2023 Corrections Issued BOBBY KEY
Pre-Inspection 2/8/2023 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 3/22/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 3/22/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/21/2023 Corrections Issued BOBBY KEY
Green Building Rough 6/21/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 7/26/2023 Approved BOBBY KEY
ELECTRICAL-Rough 7/26/2023 Corrections Issued BOBBY KEY
Green Building Rough 7/26/2023 Approved BOBBY KEY
HVAC-Rough 7/26/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 7/26/2023 Approved BOBBY KEY
ELECTRICAL-Rough 8/11/2023 Approved HERBERT GIRON
Insulation 8/11/2023 Approved HERBERT GIRON
Drywall Nailing 8/28/2023 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 8/28/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Approved BOBBY KEY
Service/Power Release 8/28/2023 Approved BOBBY KEY
Drywall Nailing 9/1/2023 Approved BOBBY KEY
HVAC-Rough 9/1/2023 Approved BOBBY KEY
ELECTRICAL-Final 1/8/2024 Approved BOBBY KEY
Final 1/8/2024 Corrections Issued BOBBY KEY
Green Building Final 1/8/2024 Approved BOBBY KEY
HVAC-Final 1/8/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 1/8/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 1/8/2024 Corrections Issued BOBBY KEY
Final 2/23/2024 OK to Issue CofO BOBBY KEY
HVAC-Final 2/23/2024 Approved BOBBY KEY
Smoke Detectors 2/23/2024 Approved BOBBY KEY