1310 W 25TH ST 90007
Certificate Information: 1310 W 25TH ST 90007
- Application / Permit
- 20014-10000-02941
- Plan Check / Job No.
- B20LA12313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO EXISTING GARAGE FOR A ONE-STORY ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 1/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | ADAM HEGAZI |
| Corrections Issued | 8/4/2020 | ADAM HEGAZI |
| Plan Check Approved | 9/25/2020 | SAMUEL GONZALEZ |
| Issued | 11/25/2020 | APPLICANT |
| Building Plans Picked Up | 12/3/2020 | APPLICANT |
| CofO in Progress | 12/20/2021 | SCOTT FINNILA |
| CofO in Progress | 12/20/2021 | SCOTT FINNILA |
| Permit Finaled | 1/5/2022 | RONALD MYRICK |
| CofO Issued | 1/5/2022 | RONALD MYRICK |
| Permit Finaled | 1/5/2022 | RONALD MYRICK |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 8/19/2020 | MELISSA JONES |
| Historic monument | Cleared | 8/19/2020 | MELISSA JONES |
| Address approval | Cleared | 8/20/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 8/20/2020 | CHINH DINH |
| Sewer availability | Cleared | 8/20/2020 | CHINH DINH |
| Community Plan Implem. Overlay | Cleared | 9/17/2020 | RAFAEL FONTES |
Contact Information
| Contractor | Perfitt John; Lic. No.: 1034808-B | 180 SOUTH CITRUS LOS ANGELES, CA 90036 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 4215 TOLAND WAY LOS ANGELES, CA 90065 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 12/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 12/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/16/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 12/16/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/17/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/5/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 1/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 1/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/8/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 1/8/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 1/8/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 2/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 2/12/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/19/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/24/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/24/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/9/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/30/2021 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 7/30/2021 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Approved | RUBEN SALAS |
| Green Building Rough | 7/30/2021 | Approved | RUBEN SALAS |
| HVAC-Rough | 7/30/2021 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 7/30/2021 | Approved | RUBEN SALAS |
| Special/Order Compliance | 7/30/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 8/12/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 8/12/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 8/26/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/7/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 9/7/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/10/2021 | Approved | RICHARD STEINBACH |
| Gas Test | 10/25/2021 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/25/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 10/25/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/1/2021 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/1/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 11/1/2021 | Approved | SABAS ALONSO |
| HVAC-Final | 11/1/2021 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/1/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 11/1/2021 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 11/1/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 11/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 11/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 11/15/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 11/15/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 11/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 11/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/8/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/17/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |