6086 W 82ND ST 90045
Certificate Information: 6086 W 82ND ST 90045
- Application / Permit
- 20014-10000-02900
- Plan Check / Job No.
- B20LA12190
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel of existing single family dwelling
- Permit Issued
- Issued on 8/4/2021
- Issuing Office
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2020 | SHANGQIN XIE |
| Corrections Issued | 7/15/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 2/5/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 5/29/2021 | RAHEL BEYENE |
| Plan Check Approved | 7/22/2021 | RAHEL BEYENE |
| Issued | 8/4/2021 | APPLICANT |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| CofO in Progress | 2/9/2023 | BOBBY KEY |
| Permit Finaled | 2/10/2023 | DANIEL ORRANTE |
| CofO Issued | 2/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | CATHERINE ADROVER |
| Construction near power lines | Cleared | 1/7/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/30/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/15/2021 | RAYMOND MUGAMBWA |
| Miscellaneous | Cleared | 5/13/2021 | JENSON LEE |
Contact Information
| Architect | Best,, Richard Allen; Lic. No.: C17334 | 1275 BEVERLY ESTATES DR. BEVERLY HILLS, CA 90210 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/2/2021 | Approved | DAVID FEILER |
| Insulation | 12/1/2021 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 12/1/2021 | Corrections Issued | BOBBY KEY |
| Insulation | 12/10/2021 | No Access for Inspection | JOHN KAYON |
| PLUMBING-Rough | 12/10/2021 | No Access for Inspection | JOHN KAYON |
| Insulation | 12/15/2021 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/15/2021 | Partial Approval | BOBBY KEY |
| Insulation | 12/16/2021 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2022 | Approved | JOHN KAYON |
| Interior/Exterior Lathing | 3/10/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/30/2022 | No Access for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/30/2022 | No Access for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/30/2022 | No Access for Inspection | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 3/30/2022 | No Access for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/5/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/5/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 4/5/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/5/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/11/2022 | Partial Approval | BOBBY KEY |
| Gas Test | 4/11/2022 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 4/11/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 4/11/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 4/14/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 4/14/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 4/19/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/19/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/19/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/19/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/19/2022 | Approved | BOBBY KEY |
| Insulation | 5/3/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/18/2022 | Not Ready for Inspection | RICHARD STEINBACH |
| Drywall Nailing | 5/23/2022 | Approved | BOBBY KEY |
| Final | 5/23/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 9/19/2022 | Corrections Issued | BOBBY KEY |
| Final | 9/19/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 9/19/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 9/19/2022 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/19/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 9/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/30/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 10/6/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 10/14/2022 | Conditional Approval | BOBBY KEY |
| Service/Power Release | 10/14/2022 | Approved | BOBBY KEY |
| HVAC-Final | 10/20/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/20/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 12/2/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 12/2/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 12/2/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 12/2/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/9/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/23/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/23/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 12/23/2022 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 12/23/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 12/28/2022 | Approved | BOBBY KEY |
| HVAC-Final | 12/30/2022 | Approved | BOBBY KEY |
| Final | 2/3/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 2/3/2023 | Approved | BOBBY KEY |
| Final | 2/9/2023 | OK to Issue CofO | BOBBY KEY |