4270 W 62ND ST 90043

Certificate Information: 4270 W 62ND ST 90043

Application / Permit
20014-10000-02885
Plan Check / Job No.
B20LA12162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ROOM ADDITION IN THE REAR DWELLING (12'x 29'-3" IRREGULAR) AND STAIR IN FRONT OF THE BUILDING
Permit Issued
Issued on 10/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 SAMUEL GONZALEZ
Corrections Issued 7/17/2020 SAMUEL GONZALEZ
Applicant returned to address corrections 9/1/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/24/2020 CRISTINA SALAZAR
Plan Check Approved 10/6/2020 RICARDO RAMIREZ
Issued 10/9/2020 APPLICANT
Building Plans Picked Up 10/9/2020 APPLICANT
CofO in Progress 2/22/2021 FREDDIE RIVERA
Permit Finaled 2/23/2021 RONALD MYRICK
CofO Issued 2/23/2021 RONALD MYRICK
Permit Finaled 2/23/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 9/11/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 9/11/2020 JUAN ASHTON
Grading Pre-Inspection Cleared 9/25/2020 SAMUEL GONZALEZ
Roof/Waste drainage to street Cleared 9/28/2020 JUAN ASHTON

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/16/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 10/20/2020 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 12/10/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 12/10/2020 Approved FREDDIE RIVERA
Structural Steel Frame 12/10/2020 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 12/16/2020 Conditional Approval FREDDIE RIVERA
HVAC-Rough 12/16/2020 Not Ready for Inspection FREDDIE RIVERA
Insulation 12/24/2020 Approved FREDDIE RIVERA
Shower Pan 12/24/2020 Approved FREDDIE RIVERA
Drywall Nailing 1/11/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/11/2021 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 2/2/2021 Approved FREDDIE RIVERA
Final 2/2/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 2/2/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 2/2/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 2/10/2021 Not Ready for Inspection FREDDIE RIVERA
Final 2/16/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 2/16/2021 Approved FREDDIE RIVERA
Smoke Detectors 2/16/2021 Approved FREDDIE RIVERA
Final 2/22/2021 OK to Issue CofO FREDDIE RIVERA