4270 W 62ND ST 90043
Certificate Information: 4270 W 62ND ST 90043
- Application / Permit
- 20014-10000-02885
- Plan Check / Job No.
- B20LA12162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ROOM ADDITION IN THE REAR DWELLING (12'x 29'-3" IRREGULAR) AND STAIR IN FRONT OF THE BUILDING
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 7/17/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 9/1/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/24/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 10/6/2020 | RICARDO RAMIREZ |
| Issued | 10/9/2020 | APPLICANT |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| CofO in Progress | 2/22/2021 | FREDDIE RIVERA |
| Permit Finaled | 2/23/2021 | RONALD MYRICK |
| CofO Issued | 2/23/2021 | RONALD MYRICK |
| Permit Finaled | 2/23/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2020 | JUAN ASHTON |
| Grading Pre-Inspection | Cleared | 9/25/2020 | SAMUEL GONZALEZ |
| Roof/Waste drainage to street | Cleared | 9/28/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/16/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 10/20/2020 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/10/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/10/2020 | Approved | FREDDIE RIVERA |
| Structural Steel Frame | 12/10/2020 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/16/2020 | Conditional Approval | FREDDIE RIVERA |
| HVAC-Rough | 12/16/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 12/24/2020 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/24/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/11/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 1/11/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/2/2021 | Approved | FREDDIE RIVERA |
| Final | 2/2/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/2/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 2/2/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Final | 2/10/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 2/16/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 2/16/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 2/16/2021 | Approved | FREDDIE RIVERA |
| Final | 2/22/2021 | OK to Issue CofO | FREDDIE RIVERA |