2338 E GATEWOOD ST 90031
Certificate Information: 2338 E GATEWOOD ST 90031
- Application / Permit
- 20014-10000-02852
- Plan Check / Job No.
- B20LA12046
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Laundry room addition and remodel of existing single family dwelling
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Current Status
- Issued on 1/6/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | RAHEL BEYENE |
| Corrections Issued | 7/17/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/8/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/30/2020 | RAHEL BEYENE |
| Plan Check Approved | 1/6/2021 | SHANGQIN XIE |
| Issued | 1/6/2021 | APPLICANT |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 8/10/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 8/26/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/26/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Marrs,, Nicholas Reidar; Lic. No.: C83398 | 1150 GENEVA ST LIVERMORE, CA 94550 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Approved | THOMAS LOGRASSO |
| Pre-Inspection | 7/30/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/2/2021 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/7/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/13/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/20/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/3/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 1/14/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/12/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/20/2022 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Rough | 5/20/2022 | Partial Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 5/20/2022 | Partial Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 5/20/2022 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 9/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 9/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/9/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 9/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 9/9/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 9/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 9/21/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 9/21/2022 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 9/21/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 10/28/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/21/2022 | No Access for Inspection | DONALD CRICHLOW |
| Interior/Exterior Lathing | 11/28/2022 | Partial Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/15/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/29/2022 | Corrections Issued | RUBEN SALAS |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | THOMAS LOGRASSO |