1416 W 79TH ST 90047

Certificate Information: 1416 W 79TH ST 90047

Application / Permit
20014-10000-02833
Plan Check / Job No.
B20LA11941
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDING A 2 STORY ADU MAX 1200, PER ORDINANCE ON THE REAR SIDE OF THE PROPERTY, ATTACHING TO (E) GARAGE & ADD GROUND LEVEL & 2ND STORY.
Permit Issued
Issued on 10/27/2020
Issuing Office
Current Status
CofO Issued on 4/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 MAHNAZ NOURHASHEMI
Corrections Issued 8/5/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 8/7/2020 JASON HEALEY
Building Plans Picked Up 8/14/2020 APPLICANT
Plan Check Approved 10/27/2020 MAHNAZ NOURHASHEMI
Issued 10/27/2020 APPLICANT
CofO in Progress 4/19/2022 LILIANA PORTILLO
Permit Finaled 4/22/2022 DEROLD HAUFF
CofO Issued 4/22/2022 DEROLD HAUFF
Permit Finaled 4/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2020 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 9/16/2020 ROSA SILVA
Sewer availability Cleared 9/16/2020 ROSA SILVA
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/22/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/23/2020 WALLIE JONG
Construction near power lines Cleared 10/26/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 12/21/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 12/21/2020 Approved ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 1/6/2021 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 1/12/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/12/2021 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/20/2021 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 1/20/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 5/6/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 5/17/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 6/17/2021 Approved HORACE FULTZ
ELECTRICAL-Rough 6/17/2021 Approved HORACE FULTZ
Gas Test 6/17/2021 Approved HORACE FULTZ
PLUMBING-Rough 6/17/2021 Approved HORACE FULTZ
HVAC-Rough 7/13/2021 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 7/13/2021 Corrections Issued EUGENE CASSIDY
HVAC-Rough 7/15/2021 Approved HORACE FULTZ
Rough-Elec/Plmb/HVAC 7/15/2021 Corrections Issued HORACE FULTZ
Insulation 7/23/2021 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/30/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 8/10/2021 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/10/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Gas Test 8/19/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/19/2021 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Final 8/19/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 2/24/2022 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 2/24/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/8/2022 Corrections Issued ANTHONY EGSON
HVAC-Final 3/8/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 3/8/2022 Corrections Issued ANTHONY EGSON
Service/Power Release 3/8/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 3/14/2022 Approved SABAS ALONSO
Final 3/14/2022 Corrections Issued SABAS ALONSO
Gas Test 3/14/2022 Approved SABAS ALONSO
HVAC-Final 3/14/2022 Approved SABAS ALONSO
PLUMBING-Final 3/14/2022 Approved SABAS ALONSO
Final 4/8/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 4/8/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Approved LILIANA PORTILLO
Final 4/18/2022 OK to Issue CofO LILIANA PORTILLO