1416 W 79TH ST 90047
Certificate Information: 1416 W 79TH ST 90047
- Application / Permit
- 20014-10000-02833
- Plan Check / Job No.
- B20LA11941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDING A 2 STORY ADU MAX 1200, PER ORDINANCE ON THE REAR SIDE OF THE PROPERTY, ATTACHING TO (E) GARAGE & ADD GROUND LEVEL & 2ND STORY.
- Permit Issued
- Issued on 10/27/2020
- Issuing Office
- Current Status
- CofO Issued on 4/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/5/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/7/2020 | JASON HEALEY |
| Building Plans Picked Up | 8/14/2020 | APPLICANT |
| Plan Check Approved | 10/27/2020 | MAHNAZ NOURHASHEMI |
| Issued | 10/27/2020 | APPLICANT |
| CofO in Progress | 4/19/2022 | LILIANA PORTILLO |
| Permit Finaled | 4/22/2022 | DEROLD HAUFF |
| CofO Issued | 4/22/2022 | DEROLD HAUFF |
| Permit Finaled | 4/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2020 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2020 | ROSA SILVA |
| Sewer availability | Cleared | 9/16/2020 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/22/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/23/2020 | WALLIE JONG |
| Construction near power lines | Cleared | 10/26/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/21/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/21/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 12/21/2020 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/21/2020 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 1/6/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 1/12/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/12/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 1/20/2021 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 1/20/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 5/6/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 5/17/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/17/2021 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 6/17/2021 | Approved | HORACE FULTZ |
| Gas Test | 6/17/2021 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 6/17/2021 | Approved | HORACE FULTZ |
| HVAC-Rough | 7/13/2021 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/13/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 7/15/2021 | Approved | HORACE FULTZ |
| Rough-Elec/Plmb/HVAC | 7/15/2021 | Corrections Issued | HORACE FULTZ |
| Insulation | 7/23/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/30/2021 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 8/10/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/10/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 8/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/19/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2022 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/8/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 3/8/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/8/2022 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 3/8/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 3/14/2022 | Approved | SABAS ALONSO |
| Final | 3/14/2022 | Corrections Issued | SABAS ALONSO |
| Gas Test | 3/14/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 3/14/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 3/14/2022 | Approved | SABAS ALONSO |
| Final | 4/8/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 4/8/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Approved | LILIANA PORTILLO |
| Final | 4/18/2022 | OK to Issue CofO | LILIANA PORTILLO |