2140 N SUNSET CREST DR 90046
Certificate Information: 2140 N SUNSET CREST DR 90046
- Application / Permit
- 20014-10000-02808
- Plan Check / Job No.
- B20LA11854
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION OF BEDROOM, POWDER AT KITHEN AND NEWTRELLIS. REMODEL OF KITCHEN, LIVING ROOM CEILING, MASTER CLOSET, MASTER BATH, & BATHROOM. NEW STAIR TO BASEMENT LEVEL.
- Permit Issued
- Issued on 6/23/2021
- Issuing Office
- Current Status
- Issued on 6/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/15/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/29/2020 | TIEN JEN WANG |
| Plan Check Approved | 2/22/2021 | MAHNAZ NOURHASHEMI |
| Issued | 6/23/2021 | APPLICANT |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 11/24/2020 | MIGUEL GAMBOA |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/21/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 1/21/2021 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2021 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 2/9/2021 | RAYMOND MUGAMBWA |
| GPI Written Notices | Cleared | 2/22/2021 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 2/22/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Contractor | Projekta Inc; Lic. No.: 1010761-B | 1215 N RED GUM STREET #F ANAHEIM, CA 92806 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2021 | Conditional Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 11/30/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 11/30/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 11/30/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/30/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 12/9/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/9/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 12/9/2021 | Partial Inspection | RAUL BARAJAS |
| Shower Pan | 12/9/2021 | Approved | RAUL BARAJAS |
| Insulation | 12/27/2021 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/30/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/3/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/11/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/11/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 4/29/2022 | Corrections Issued | RAUL BARAJAS |
| Final | 6/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 6/6/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/6/2022 | Approved | ALIZAH MAYAGOITIA |