2140 N SUNSET CREST DR 90046

Certificate Information: 2140 N SUNSET CREST DR 90046

Application / Permit
20014-10000-02808
Plan Check / Job No.
B20LA11854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION OF BEDROOM, POWDER AT KITHEN AND NEWTRELLIS. REMODEL OF KITCHEN, LIVING ROOM CEILING, MASTER CLOSET, MASTER BATH, & BATHROOM. NEW STAIR TO BASEMENT LEVEL.
Permit Issued
Issued on 6/23/2021
Issuing Office
Current Status
Issued on 6/23/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/10/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 MAHNAZ NOURHASHEMI
Corrections Issued 9/15/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 9/29/2020 TIEN JEN WANG
Plan Check Approved 2/22/2021 MAHNAZ NOURHASHEMI
Issued 6/23/2021 APPLICANT
Building Plans Picked Up 6/29/2021 APPLICANT

Permit Application Clearance Information

ZI Cleared 11/24/2020 MIGUEL GAMBOA
BHO/Hillside ordinance Cleared 12/23/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 12/23/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 12/23/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 1/21/2021 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 1/21/2021 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 2/9/2021 RAYMOND MUGAMBWA
Roof/Waste drainage to street Cleared 2/9/2021 RAYMOND MUGAMBWA
GPI Written Notices Cleared 2/22/2021 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 2/22/2021 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Contractor Projekta Inc; Lic. No.: 1010761-B 1215 N RED GUM STREET #F      ANAHEIM, CA 92806
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2021 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 11/30/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 11/30/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 11/30/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 11/30/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/9/2021 Approved RAUL BARAJAS
ELECTRICAL-Rough 12/9/2021 Approved RAUL BARAJAS
Green Building Rough 12/9/2021 Partial Inspection RAUL BARAJAS
Shower Pan 12/9/2021 Approved RAUL BARAJAS
Insulation 12/27/2021 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 12/27/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 12/30/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 1/3/2022 Approved RAUL BARAJAS
Drywall Nailing 1/11/2022 Approved RAUL BARAJAS
Green Building Rough 1/11/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Not Ready RAUL BARAJAS
Final 4/29/2022 Corrections Issued RAUL BARAJAS
Final 6/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 6/6/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 6/6/2022 Approved ALIZAH MAYAGOITIA