8223 N LOUISE AVE 91325

Certificate Information: 8223 N LOUISE AVE 91325

Application / Permit
20014-10000-02807
Plan Check / Job No.
B20LA11853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNITADDITION TO EXISTING DETACHED GARAGE PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d) & (g).
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 CRISTINA SALAZAR
Corrections Issued 7/10/2020 CRISTINA SALAZAR
Applicant returned to address corrections 9/15/2020 ZAW HAN
Plan Check Approved 12/14/2020 GEORGE ALVAREZ
Building Plans Picked Up 12/15/2020 APPLICANT
Issued 2/3/2021 APPLICANT
CofO in Progress 5/16/2022 RAUL OLAGI
Permit Finaled 5/24/2022 RONALD MYRICK
CofO Issued 5/24/2022 RONALD MYRICK
Permit Finaled 5/24/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/10/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/10/2020 ADRIAN CASTRO
Sewer availability Cleared 8/10/2020 ADRIAN CASTRO
Low Impact Development Cleared 11/14/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 11/16/2020 ADRIAN CASTRO

Contact Information

Contractor Master Serve Restoration Inc; Lic. No.: 940414-B 12473-J GLADSTONE AVENUE      SYLMAR, CA 91342
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/10/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 2/16/2021 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 3/1/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/9/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 4/9/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Approved ARTHUR SARGSYAN
Green Building Rough 4/9/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/9/2021 Approved ARTHUR SARGSYAN
Insulation 4/21/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/21/2021 Approved ARTHUR SARGSYAN
Shower Pan 4/21/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 5/6/2021 Approved MORRIS JACKSON
Special/Order Compliance 5/6/2021 Partial Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/19/2021 Approved RAUL OLAGI
ELECTRICAL-Final 11/19/2021 Corrections Issued RAUL OLAGI
Final 11/19/2021 Corrections Issued RAUL OLAGI
Green Building Final 11/19/2021 Corrections Issued RAUL OLAGI
PLUMBING-Final 11/19/2021 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 11/19/2021 Not Ready for Inspection RAUL OLAGI
Final 1/14/2022 Corrections Issued RAUL OLAGI
Green Building Final 1/14/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/14/2022 Approved RAUL OLAGI
Final 4/25/2022 Corrections Issued RAUL OLAGI
Gas Test 4/25/2022 Approved RAUL OLAGI
Green Building Final 4/25/2022 Approved RAUL OLAGI
Final 5/16/2022 OK to Issue CofO RAUL OLAGI