17401 W RANCHO ST 91316
Certificate Information: 17401 W RANCHO ST 91316
- Application / Permit
- 20014-10000-02805
- Plan Check / Job No.
- B20LA11832
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- First and second floor additions to an (E) SFD with attached garage, including major remodel to (E) SFD and garage. Fire sprinkler is provided throughout the building. 1 OF 2
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 8/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | HELEN NGUYEN |
| Corrections Issued | 8/19/2020 | DEAN LEE |
| Quality Review Completed | 8/31/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| Applicant returned to address corrections | 12/3/2020 | DEAN LEE |
| Applicant returned to address corrections | 2/10/2021 | DEAN LEE |
| Applicant returned to address corrections | 2/17/2021 | DEAN LEE |
| Applicant returned to address corrections | 3/13/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/6/2021 | HELEN NGUYEN |
| Plan Check Approved | 5/11/2021 | HELEN NGUYEN |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 6/17/2022 | SEAN HAUPT |
| Permit Finaled | 8/9/2022 | MICHAEL SMITH |
| CofO Issued | 8/9/2022 | MICHAEL SMITH |
| Permit Finaled | 8/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 1/5/2021 | MARC WOERSCHING |
| Address approval | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Watercourse | Cleared | 1/6/2021 | ADRIAN CASTRO |
| ZI | Cleared | 1/19/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 2/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/25/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/1/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 6/1/2021 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 6/2/2021 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 6/11/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 6/11/2021 | Approved | STEVEN BACK |
| Deputy Steel/Welding | 6/17/2021 | Conditional Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Partial Approval | PETER FOLLING |
| Deputy Wood Construction | 9/16/2021 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/17/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 10/14/2021 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 10/14/2021 | Conditional Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 10/28/2021 | Approved | SEAN HAUPT |
| HVAC-Rough | 10/28/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/1/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 11/1/2021 | Approved | SEAN HAUPT |
| Insulation | 11/12/2021 | Approved | SEAN HAUPT |
| Drywall Nailing | 11/29/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/29/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/10/2021 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 5/5/2022 | Corrections Issued | SEAN HAUPT |
| Final | 5/5/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 5/5/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 5/5/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 5/5/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 5/5/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 5/5/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 6/17/2022 | Approved | SEAN HAUPT |
| Final | 6/17/2022 | OK to Issue CofO | SEAN HAUPT |
| HVAC-Final | 6/17/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 6/17/2022 | Approved | SEAN HAUPT |