6750 N NAGLE AVE 91401
Certificate Information: 6750 N NAGLE AVE 91401
- Application / Permit
- 20014-10000-02790
- Plan Check / Job No.
- B20LA11764
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO EXISTING DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | STANLEY RAAP |
| Corrections Issued | 7/15/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 9/22/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
| Applicant returned to address corrections | 12/8/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 8/5/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 2/28/2022 | STANLEY RAAP |
| Plan Check Approved | 5/5/2022 | SHANGQIN XIE |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 6/27/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
| CofO Issued | 7/31/2024 | RUBEN SALAS |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/9/2021 | JASON CHAN |
| ZA Case | Cleared | 2/9/2021 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 2/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | JOHN LIN |
| Address approval | Cleared | 2/22/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/4/2022 | Corrections Issued | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 10/19/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 10/19/2022 | Approved | WILLIAM WREN |
| Gas Test | 10/19/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 10/19/2022 | Approved | WILLIAM WREN |
| Sewer | 10/19/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 10/19/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 2/24/2023 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 2/24/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 2/24/2023 | Corrections Issued | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 7/14/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 7/26/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 7/26/2023 | Approved | KIRK SANDERS |
| Insulation | 8/8/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 8/14/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/14/2023 | Approved | JUAN VALENZUELA |
| Shower Pan | 8/14/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/9/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 5/9/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 5/14/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/28/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 5/28/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/6/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 6/14/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/14/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/14/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/14/2024 | Approved | OGANES TARAKHCHYAN |