1718 S HOBART BLVD 90006
Certificate Information: 1718 S HOBART BLVD 90006
- Application / Permit
- 20014-10000-02765
- Plan Check / Job No.
- B20LA11677
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) STORAGE TO ACCESSORY DWELLING UNIT WITH TWO STORY ADDITION. "COMPLY WITH DEPARTMENT ORDER effective date 05/22/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 898685.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 12/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | GEORGE ALVAREZ |
| Corrections Issued | 7/29/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 1/22/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 1/25/2021 | APPLICANT |
| Plan Check Approved | 6/13/2022 | JOSEPH RAFOLS |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 7/30/2025 | WILLIAM MICHALAK |
| CofO Issued-Status Void | 11/17/2025 | CLAUDIO MORENO |
| Permit Finaled-Status Void | 11/17/2025 | CLAUDIO MORENO |
| Re-Activate Permit | 12/18/2025 | CLAUDIO MORENO |
| Permit Finaled | 12/22/2025 | CLAUDIO MORENO |
| CofO Corrected | 12/22/2025 | CLAUDIO MORENO |
| Permit Finaled | 12/22/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 7/26/2021 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | WALLIE JONG |
| Address approval | Cleared | 8/20/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/23/2021 | JEANIE LAM |
| HPOZ | Cleared | 2/23/2022 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 2/23/2022 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 2/23/2022 | LAMBERT GIESSINGER |
| Low Impact Development | Cleared | 3/25/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/4/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/2/2022 | No Access for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 9/16/2022 | Partial Approval | WILLIAM MICHALAK |
| Pre-Inspection | 9/16/2022 | Approved | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 10/7/2022 | No Access for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 10/26/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Deputy Drilled-In Anchors | 11/15/2022 | Approved | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 11/22/2022 | Approved | WILLIAM MICHALAK |
| Deputy Drilled-In Anchors | 12/22/2022 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 1/24/2023 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 2/1/2023 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 2/9/2023 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 3/8/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Pre-Inspection | 5/26/2023 | Approved | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Pre-Inspection | 6/23/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 6/30/2023 | Approved | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Wood Frame | 9/14/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 10/17/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Wood Frame | 3/6/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Wood Frame | 3/27/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 4/8/2024 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 4/8/2024 | Corrections Issued | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 6/26/2024 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/16/2024 | Corrections Issued | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 7/16/2024 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 7/16/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 8/20/2024 | Approved | WILLIAM MICHALAK |
| Insulation | 10/22/2024 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | WILLIAM MICHALAK |
| Shower Pan | 10/22/2024 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 10/29/2024 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Not Ready | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/25/2025 | Approved | WILLIAM MICHALAK |
| Final | 6/25/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 6/25/2025 | Approved | WILLIAM MICHALAK |
| Green Building Rough | 6/25/2025 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 6/25/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 6/26/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 6/26/2025 | Approved | WILLIAM MICHALAK |
| Final | 7/1/2025 | Conditional Approval | WILLIAM MICHALAK |
| Final | 7/30/2025 | OK to Issue CofO | WILLIAM MICHALAK |