6208 S 6TH AVE 90043
Certificate Information: 6208 S 6TH AVE 90043
- Application / Permit
- 20014-10000-02764
- Plan Check / Job No.
- B20LA11660
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED [11 ft x 16 ft] GARAGE TO ACCESSORY DWELLING UNIT & ADD [25 FT X 26 FT] ADDITION PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 9/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | JESSE JIMENEZ |
| Corrections Issued | 7/9/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 9/2/2020 | AMIR DANAI |
| Applicant returned to address corrections | 11/2/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 9/3/2021 | RICARDO RAMIREZ |
| Issued | 9/29/2021 | APPLICANT |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | ENRIQUE MIRELES |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | THOMAS LANG |
| Sewer availability | Cleared | 9/29/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 4/26/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 7/14/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/16/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/20/2021 | THOMAS LANG |
Contact Information
| Contractor | Altera Construction; Lic. No.: 1036431-B | 211 W 92ND STREET LOS ANGELES, CA 90003 |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 18119 S PRAIRIE AVE 102 TORRANCE, CA 90504 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/10/2021 | Corrections Issued | FREDDIE RIVERA |
| Pre-Inspection | 11/10/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 11/19/2021 | Corrections Issued | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 11/19/2021 | Not Ready for Inspection | DANIEL GONZALEZ |
| Gas Test | 11/19/2021 | Partial Approval | DANIEL GONZALEZ |
| PLUMBING-Rough | 11/19/2021 | Corrections Issued | DANIEL GONZALEZ |
| Sewer | 11/19/2021 | Not Ready for Inspection | DANIEL GONZALEZ |
| Underground Mechanical | 11/19/2021 | Partial Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 11/24/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 11/24/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 1/24/2022 | Corrections Issued | FREDDIE RIVERA |
| Deputy Wood Construction | 1/28/2022 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/31/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Approved | FREDDIE RIVERA |
| Gas Test | 1/31/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/31/2022 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 1/31/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 1/31/2022 | Approved | FREDDIE RIVERA |
| Insulation | 2/4/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/4/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/10/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 2/10/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 2/15/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/15/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/27/2022 | Approved | ENRIQUE MIRELES |
| Final | 5/27/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 5/27/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/27/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 5/27/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 5/27/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/6/2022 | Approved | ENRIQUE MIRELES |
| Final | 7/6/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 7/6/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/6/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/11/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 7/13/2022 | OK to Issue CofO | ENRIQUE MIRELES |