230-230 1/2 W 78TH ST 90003

Certificate Information: 230-230 1/2 W 78TH ST 90003

Application / Permit
20014-10000-02747
Plan Check / Job No.
B20LA11595
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
GROUND FLOOR ADDITION CONNECT TWO SFD TO CREATE DUPLEX. (1 OF 2)
Permit Issued
Issued on 8/10/2022
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 JOE VO
Corrections Issued 7/28/2020 JOE VO
Quality Review Completed 8/27/2020 MINYE PAK
Applicant returned to address corrections 3/14/2021 JOE VO
Applicant returned to address corrections 8/17/2021 JOE VO
Plan Check Approved 8/10/2022 JOE VO
Issued 8/10/2022 APPLICANT
CofO in Progress 1/31/2023 STUART CHAPMAN
CofO in Progress 1/31/2023 DONALD CRICHLOW
CofO in Progress 2/17/2023 LILIANA PORTILLO
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/15/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/20/2021 JEANIE LAM
Sewer availability Cleared 2/11/2021 PAMELA TENEZA
Low Impact Development Cleared 7/7/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/16/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: NA65104       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/26/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 8/26/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/9/2022 Partial Approval LILIANA PORTILLO
Insulation 9/19/2022 Corrections Issued LILIANA PORTILLO
Shower Pan 9/19/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 9/26/2022 Approved LILIANA PORTILLO
Shower Pan 9/26/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/6/2022 Approved LILIANA PORTILLO
Final 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/6/2022 Approved LILIANA PORTILLO
Green Building Final 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 12/6/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Final 1/11/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 1/11/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/11/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 1/11/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Final 1/30/2023 Approved STUART CHAPMAN
Final 1/30/2023 Partial Approval STUART CHAPMAN
Green Building Final 1/30/2023 Approved STUART CHAPMAN
HVAC-Final 1/30/2023 Approved STUART CHAPMAN
PLUMBING-Final 1/30/2023 Approved STUART CHAPMAN
Smoke Detectors 1/30/2023 Approved STUART CHAPMAN