306 N ARDEN BLVD 90004
Certificate Information: 306 N ARDEN BLVD 90004
- Application / Permit
- 20014-10000-02721
- Plan Check / Job No.
- B20LA11478
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) 18' X 20.5' DETACHED GARAGE TO 2 STORY ADU 680 SF PER 12.22 A33 C & E, SEE COMMENTS
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | STARR CHEN |
| Corrections Issued | 7/25/2020 | STARR CHEN |
| Quality Review Completed | 8/14/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/25/2020 | APPLICANT |
| Applicant returned to address corrections | 1/11/2021 | STARR CHEN |
| Applicant returned to address corrections | 7/15/2021 | STARR CHEN |
| Applicant returned to address corrections | 8/31/2021 | STARR CHEN |
| Applicant returned to address corrections | 1/14/2022 | STARR CHEN |
| Applicant returned to address corrections | 2/3/2022 | STARR CHEN |
| Plan Check Approved | 3/18/2022 | STARR CHEN |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 2/13/2024 | LILIANA PORTILLO |
| CofO in Progress | 2/13/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 2/14/2024 | LILIANA PORTILLO |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2020 | JAMES KHO |
| Sewer availability | Cleared | 10/20/2020 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | JAMES KHO |
| Low Impact Development | Cleared | 12/15/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 1/12/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 6/18/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/18/2021 | RIDWAN HARDY |
Contact Information
| Contractor | C A Construction; Lic. No.: 819826-B | 5115 BRYNHURST AVENUE LOS ANGELES, CA 90043 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/20/2022 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Barrier | 9/20/2022 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Subgrade | 9/20/2022 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 10/7/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 10/7/2022 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 10/13/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/14/2022 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 10/14/2022 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 10/14/2022 | Approved | JEFFREY MEAD |
| Deputy Steel/Welding | 12/5/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 2/7/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 2/24/2023 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/24/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/2/2023 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 3/2/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/2/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 3/2/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/6/2023 | Corrections Issued | JEFFREY MEAD |
| Shower Pan | 3/6/2023 | Approved | JEFFREY MEAD |
| Insulation | 3/9/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 3/15/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/15/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/19/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Sewer | 5/19/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 5/19/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 5/25/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 5/25/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Green Building Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| HVAC-Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 7/28/2023 | Not Ready for Inspection | DONALD CRICHLOW |
| HVAC-Final | 7/28/2023 | Not Ready for Inspection | DONALD CRICHLOW |
| PLUMBING-Final | 7/28/2023 | Not Ready for Inspection | DONALD CRICHLOW |
| ELECTRICAL-Final | 8/16/2023 | No Access for Inspection | JEFFREY MEAD |
| HVAC-Final | 8/16/2023 | No Access for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 8/16/2023 | No Access for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 8/22/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 8/22/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 8/22/2023 | Approved | JEFFREY MEAD |
| Final | 10/11/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 10/11/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 10/11/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 2/9/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 2/9/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Smoke Detectors | 2/9/2024 | Approved | LILIANA PORTILLO |
| Final | 2/13/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 2/13/2024 | Approved | LILIANA PORTILLO |