24423 S SEAGROVE AVE 90744
Certificate Information: 24423 S SEAGROVE AVE 90744
- Application / Permit
- 20014-10000-02712
- Plan Check / Job No.
- B20LA11444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (MSTR BDR 15' X 24'4" AND PATIO 6'X9'8") TO (E) ONE STORY SFD AT THE REAR OF THE STRUCTURE
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | GEORGE ALVAREZ |
| Corrections Issued | 7/13/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 9/3/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/15/2020 | ZAW HAN |
| Plan Check Approved | 9/29/2020 | ZAW HAN |
| Issued | 10/5/2020 | APPLICANT |
| Building Plans Picked Up | 10/6/2020 | APPLICANT |
| CofO in Progress | 6/3/2021 | JOHN KLARIN |
| CofO in Progress | 7/21/2021 | JOHN KLARIN |
| CofO in Progress | 4/13/2022 | ANSON MAGLASANG |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2020 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 9/11/2020 | CHINH DINH |
| Sewer availability | Cleared | 9/11/2020 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vo,, Tung Thanh; Lic. No.: C69546 | 11122 BIXLER CIRCLE GARDEN GROVE, CA 92840 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/15/2020 | Corrections Issued | DAVID FEILER |
| METHANE-Barrier | 10/15/2020 | Approved | DAVID FEILER |
| METHANE-Subgrade | 10/15/2020 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 10/21/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 10/28/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Inspection | JOHN KLARIN |
| Insulation | 11/23/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/7/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 12/7/2020 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Rough | 12/7/2020 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/14/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 12/14/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 12/14/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 12/14/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/14/2020 | Approved | JOHN KLARIN |
| Insulation | 12/22/2020 | Corrections Issued | JOHN KLARIN |
| Interior/Exterior Lathing | 12/22/2020 | Partial Approval | JOHN KLARIN |
| Insulation | 12/29/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 1/5/2021 | Approved | JOHN KLARIN |
| Final | 2/11/2021 | No Access for Inspection | JOHN KLARIN |
| Green Building Final | 2/11/2021 | No Access for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Not Required | JOHN KLARIN |
| Smoke Detectors | 2/11/2021 | No Access for Inspection | JOHN KLARIN |
| Final | 2/22/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 2/22/2021 | Corrections Issued | JOHN KLARIN |
| Smoke Detectors | 2/22/2021 | Approved | JOHN KLARIN |
| Pre-Inspection | 4/28/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 6/2/2021 | Approved | JOHN KLARIN |
| Final | 6/2/2021 | OK to Issue CofO | JOHN KLARIN |
| Green Building Final | 6/2/2021 | Approved | JOHN KLARIN |
| HVAC-Final | 6/2/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/2/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/12/2021 | Corrections Issued | JOHN KLARIN |