17854 W VALERIO ST 91335
Certificate Information: 17854 W VALERIO ST 91335
- Application / Permit
- 20014-10000-02688
- Plan Check / Job No.
- B20LA11415
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY ADDITION TO EXISTING SFD COMPLY WITH DEPARTMENT ORDER effective date 12/18/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Valley
- Current Status
- Issued on 8/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | CARLOS MONTES |
| Corrections Issued | 7/27/2020 | CARLOS MONTES |
| Quality Review Completed | 8/22/2020 | PRANITA SHAH |
| Building Plans Picked Up | 9/1/2020 | APPLICANT |
| Applicant returned to address corrections | 10/12/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 10/25/2022 | CARLOS MONTES |
| Plan Check Approved | 11/10/2022 | CARLOS MONTES |
| Issued | 8/29/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/30/2020 | ADRIAN CASTRO |
| ZA Case | Cleared | 5/12/2022 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 9/12/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/6/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Beck,, Charles Joseph; Lic. No.: C19289 | 129 WEST PONDERA STREET LANCASTER, CA 93534 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/26/2024 | Corrections Issued | JEFFREY BULL |
| Underground Mechanical | 9/26/2024 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 1/2/2025 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/2/2025 | Approved | DAVID SCANTLIN |
| Wood Frame | 2/27/2025 | Approved | JUAN ALVARADO |
| Deputy Wood Construction | 4/14/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Rough | 10/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Wood Frame | 10/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 11/3/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Rough | 2/12/2026 | Corrections Issued | JUAN ALVARADO |
| HVAC-Rough | 2/12/2026 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 2/12/2026 | Corrections Issued | JUAN ALVARADO |
| ELECTRICAL-Rough | 3/9/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 3/9/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/9/2026 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/9/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/12/2026 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Rough | 3/12/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 3/12/2026 | Corrections Issued | JUAN ALVARADO |
| ELECTRICAL-Rough | 4/8/2026 | Approved | JUAN ALVARADO |
| HVAC-Rough | 4/8/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 4/8/2026 | Approved | JUAN ALVARADO |