926-928 1/4 E 57TH ST 90011

Certificate Information: 926-928 1/4 E 57TH ST 90011

Application / Permit
20014-10000-02655
Plan Check / Job No.
B20LA11310
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW ATTACHED 2-STORY ADU PER CA GOVT CODE 65852.2( e)(1)(B) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/3/2022
Issuing Office
Current Status
CofO Issued on 4/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 MAHNAZ NOURHASHEMI
Corrections Issued 7/30/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 8/6/2020 TIEN JEN WANG
Building Plans Picked Up 8/11/2020 APPLICANT
Applicant returned to address corrections 7/1/2021 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 12/27/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 2/3/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 2/3/2022 MAHNAZ NOURHASHEMI
Issued 2/3/2022 APPLICANT
CofO in Progress 4/26/2023 BRENDAN MORELLI
Permit Finaled 4/30/2023 DEROLD HAUFF
Permit Finaled 4/30/2023 DEROLD HAUFF
CofO Issued 4/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/8/2020 THOMAS LANG
Sewer availability Cleared 10/8/2020 THOMAS LANG
Redevelopment Project Area Cleared 1/8/2021 GRACIELA ACOSTA
Redevelopment Project Area Cleared 1/8/2021 GRACIELA ACOSTA
Low Impact Development Cleared 6/15/2021 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/18/2021 THAN WIN
Address approval Cleared 7/7/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/14/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 3/18/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 3/22/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/22/2022 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 3/22/2022 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 3/22/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 3/22/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 3/23/2022 No Access for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 3/29/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/29/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/23/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/23/2022 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 5/23/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 5/23/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 5/23/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/23/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/31/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 5/31/2022 No Access for Inspection SHAVONNE ESPINOZA
Green Building Rough 5/31/2022 No Access for Inspection SHAVONNE ESPINOZA
HVAC-Rough 5/31/2022 No Access for Inspection SHAVONNE ESPINOZA
PLUMBING-Rough 5/31/2022 No Access for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Rough 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/17/2022 Approved HORACE FULTZ
ELECTRICAL-Rough 6/17/2022 Approved HORACE FULTZ
Green Building Rough 6/17/2022 Approved HORACE FULTZ
PLUMBING-Rough 6/17/2022 Approved HORACE FULTZ
ELECTRICAL-Rough 6/21/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 6/21/2022 Approved JOAQUIN GREENOUGH
Insulation 6/24/2022 Partial Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/24/2022 Partial Approval JOAQUIN GREENOUGH
Shower Pan 6/24/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 7/1/2022 Partial Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/1/2022 Partial Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/6/2022 No Access for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval RYAN SALAZAR
Wood Frame 8/5/2022 Approved RYAN SALAZAR
Sewer 9/26/2022 Approved RYAN SALAZAR
Underground Mechanical 9/26/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 11/16/2022 Corrections Issued SCOTT FINNILA
HVAC-Final 11/16/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Final 11/16/2022 Corrections Issued SCOTT FINNILA
Gas Test 12/5/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 12/5/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/8/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Final 2/15/2023 Approved BRENDAN MORELLI
HVAC-Final 2/15/2023 Conditional Approval BRENDAN MORELLI
Gas Test 2/22/2023 Corrections Issued BRENDAN MORELLI
Service/Power Release 2/22/2023 Approved BRENDAN MORELLI
Drywall Nailing 4/19/2023 Approved BRENDAN MORELLI
Final 4/19/2023 Corrections Issued BRENDAN MORELLI
Gas Test 4/19/2023 Approved BRENDAN MORELLI
Green Building Final 4/19/2023 Conditional Approval BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 4/19/2023 Approved BRENDAN MORELLI
Final 4/25/2023 OK to Issue CofO BRENDAN MORELLI
Green Building Final 4/25/2023 Approved BRENDAN MORELLI