3036 W CASTLE ST 90039

Certificate Information: 3036 W CASTLE ST 90039

Application / Permit
20014-10000-02643
Plan Check / Job No.
B20LA11246
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND THE EXISTING ATTACHED GARAGE, ALTERATE THE MAIN ENTRANCE AND ADD LIVING ROOM ON THE 2ND FLOOR.
Permit Issued
Issued on 10/15/2020
Issuing Office
Current Status
CofO Issued on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 JOHNNY WU
Corrections Issued 7/29/2020 JOHNNY WU
Quality Review Completed 8/12/2020 KESETE HAREGOT
Building Plans Picked Up 8/14/2020 APPLICANT
Applicant returned to address corrections 8/25/2020 JOHNNY WU
Applicant returned to address corrections 9/22/2020 JOHNNY WU
Applicant returned to address corrections 9/23/2020 JOHNNY WU
Applicant returned to address corrections 9/30/2020 JOHNNY WU
Applicant returned to address corrections 10/8/2020 JOHNNY WU
Plan Check Approved 10/15/2020 JOHNNY WU
Issued 10/15/2020 APPLICANT
CofO in Progress 11/5/2021 HAMIK HARTOUNIAN
Permit Finaled 12/3/2021 DEROLD HAUFF
CofO Issued 12/3/2021 DEROLD HAUFF
Permit Finaled 12/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/23/2020 JOHNNY WU
BHO/Hillside ordinance Cleared 10/8/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/8/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/8/2020 RENZ SORIANO
Sewer availability Cleared 10/8/2020 RENZ SORIANO

Contact Information

Architect Khalsa,, Jai Pal Singh; Lic. No.: C21066 4519 ADMIRALTY WAY STE A      MARINA DEL REY, CA 90292
Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/20/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 10/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 10/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Special/Order Compliance 10/29/2020 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 11/2/2020 Approved DAVID CHAN
PLUMBING-Rough 11/2/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 1/19/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 1/19/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/17/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 3/17/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/8/2021 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 4/16/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 4/16/2021 Approved KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 4/16/2021 Approved KATHRYN BUTTERWORTH
Insulation 4/21/2021 Approved RUBEN SALAS
Drywall Nailing 4/30/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 5/7/2021 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 6/29/2021 Conditional Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 7/12/2021 Partial Inspection THOMAS LOGRASSO
Final 10/26/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 10/26/2021 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 10/26/2021 Approved THOMAS LOGRASSO
Final 11/1/2021 Partial Approval THOMAS LOGRASSO
Final 11/4/2021 OK to Issue CofO HAMIK HARTOUNIAN