2206 1/2 W 31ST ST 90018
Certificate Information: 2206 1/2 W 31ST ST 90018
- Application / Permit
- 20014-10000-02639
- Plan Check / Job No.
- B20LA11233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ATTACHED ADU ABOVE (E) PATIO AND GARAGE. 2-STORY
- Permit Issued
- Issued on 12/10/2020
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | CARLOS MONTES |
| Corrections Issued | 7/21/2020 | CARLOS MONTES |
| Quality Review Completed | 7/30/2020 | PRANITA SHAH |
| Building Plans Picked Up | 8/3/2020 | APPLICANT |
| Applicant returned to address corrections | 12/2/2020 | CARLOS MONTES |
| Plan Check Approved | 12/10/2020 | CARLOS MONTES |
| Issued | 12/10/2020 | APPLICANT |
| CofO in Progress | 11/8/2021 | SABAS ALONSO |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 10/7/2020 | PAMELA TENEZA |
| Low Impact Development | Cleared | 10/20/2020 | JORGE MEJIA LEMUS |
| HPOZ | Cleared | 11/12/2020 | MAX LODER |
| ZI | Cleared | 11/12/2020 | MAX LODER |
| ZI | Cleared | 11/12/2020 | MAX LODER |
| ZI | Cleared | 11/12/2020 | MAX LODER |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | THOMAS LANG |
Contact Information
| Contractor | Superior Restoration; Lic. No.: 983759-B | 27890 CLINTON KEITH RD #D467 MURRIETA, CA 92562 |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/1/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 2/1/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 2/1/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | ROBERT MCDOWELL |
| METHANE-Rough | 3/9/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/4/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/4/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 5/4/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/4/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 5/11/2021 | No Access for Inspection | AMY COLIN |
| Pre-Inspection | 5/11/2021 | Partial Inspection | WILLIAM WREN |
| Insulation | 5/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/13/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 5/17/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 5/17/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 9/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| Structural Steel Frame | 9/30/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 10/5/2021 | Approved | SABAS ALONSO |
| Final | 10/5/2021 | Corrections Issued | SABAS ALONSO |
| Final | 11/5/2021 | OK to Issue CofO | SABAS ALONSO |
| Smoke Detectors | 11/5/2021 | Approved | SABAS ALONSO |